REMODEL TO (E) 2-STORY S.F.D. TO REMODEL(E) KITCHEN, REPLACE (E) WINDOWS TO (N) DOORS, ADD (N) DOORS, REMODEL (E) BATHROOMS AND (E) CLOSETS, CONVERT (E) CLOSET TO (N) HALLWAY, CREATE (N) POWDER ROOM, AND REMOVE (E) WINDOWS ON 1ST FLOOR. REMODEL AND EXPAND (E) BATHROOM ON 2ND FLOOR. ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/22/2023
Issuing Office
Valley
Current Status
Issued on 2/22/2023

Permit Application Status History

Submitted 11/17/2022 APPLICANT
Assigned to Plan Check Engineer 11/18/2022 SERGIO MUNIZ
Corrections Issued 11/19/2022 SERGIO MUNIZ
Building Plans Picked Up 12/2/2022 APPLICANT
Applicant returned to address corrections 1/20/2023 DANIEL ABRAMYAN
Issued 2/22/2023 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/17/2023 KIRK LINKLATER

Contact Information

Contractor Mg All Construction; Lic. No.: 1082580-B 20201 SHERMAN WAY STE 101B      WINNETKA, CA 91306
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/23/2023 Conditional Approval JESUS PINEDA
Pre-Inspection 5/5/2023 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 5/9/2023 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 5/9/2023 Approved CARLOS MATAMOROS
MERV13>=Rough 5/9/2023 Approved CARLOS MATAMOROS
PLUMBING-Rough 5/12/2023 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 5/17/2023 Approved CARLOS MATAMOROS
HVAC-Rough 5/17/2023 Approved CARLOS MATAMOROS
Insulation 5/17/2023 Approved CARLOS MATAMOROS
Shower Pan 5/17/2023 Approved CARLOS MATAMOROS
Insulation 5/22/2023 Approved CARLOS MATAMOROS
Shower Pan 5/22/2023 Approved CARLOS MATAMOROS
Drywall Nailing 6/2/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 6/2/2023 Approved CARLOS MATAMOROS
Gas Test 9/27/2023 Approved CARLOS MATAMOROS
MERV13>=Final 9/27/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/27/2023 SGSOV Approved CARLOS MATAMOROS
Smoke Detectors 9/27/2023 Approved CARLOS MATAMOROS