2293 N BRONSON HILL DR 90068

Certificate Information: 2293 N BRONSON HILL DR 90068

Application / Permit
22016-20000-34625
Plan Check / Job No.
B22VN16926
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REPLACE (E) BALCONY (5' x 25') OF (E) SINGLE FAMILY DWELLING AND UNDERPIN (E) FOOTING; "COMPLY WITH DEPARTMENT ORDER effective date 10/27/2015. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 4/23/2024
Issuing Office
Current Status
Permit Finaled on 5/8/2025

Permit Application Status History

Submitted 11/15/2022 APPLICANT
Assigned to Plan Check Engineer 12/8/2022 SEAN SHAHMIRI
Corrections Issued 12/19/2022 SEAN SHAHMIRI
Quality Review Completed 12/21/2022 OMID HEDAYAT
Building Plans Picked Up 1/4/2023 APPLICANT
Applicant returned to address corrections 10/31/2023 SEAN SHAHMIRI
Plan Check Approved 12/27/2023 SEAN SHAHMIRI
Issued 4/23/2024 APPLICANT
Permit Finaled 5/6/2025 JOEL ORDAZ

Permit Application Clearance Information

"D" conditions Cleared 8/1/2023 DANALYNN DOMINGUEZ
ZI Cleared 8/1/2023 DANALYNN DOMINGUEZ
Roof/Waste drainage to street Cleared 9/26/2023 DAVID VO
Eng Process Fee Ord 176,300 Cleared 9/28/2023 DAVID VO

Contact Information

Contractor D And M General Constructor Inc; Lic. No.: 745510-B 6520 PLATT AVE #551      WEST HILLS, CA 91307
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040
Geologist Schick,, John Wayne; Lic. No.: EG1300 7650 HASKELL AVENUE STE D      VAN NUYS, CA 91406

Inspector Information

JOEL ORDAZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
PTOLEMY HILL, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVAKIAN, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
EDMOND DECKERT, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
TIMOTHY KEY, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT CHAVEZ, (213) 252-3049 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/16/2024 Approved JOEL ORDAZ
Piling/Pier/Caisson 7/19/2024 Not Ready for Inspection JONATHAN FRANCHINI
Piling/Pier/Caisson 7/22/2024 No Access for Inspection JOEL ORDAZ
Piling/Pier/Caisson 7/24/2024 Approved JOEL ORDAZ
Piling/Pier/Caisson 7/26/2024 Partial Approval JOEL ORDAZ
Piling/Pier/Caisson 7/30/2024 Approved JOEL ORDAZ
Deputy Reinf. Concrete 8/2/2024 Approved JOEL ORDAZ
Deputy Drilled-In Anchors 8/15/2024 Approved JOEL ORDAZ
Footing/Foundation/Slab 8/19/2024 Not Ready for Inspection JOEL ORDAZ
Piling/Pier/Caisson 8/19/2024 Not Ready for Inspection JOEL ORDAZ
Footing/Foundation/Slab 8/26/2024 Approved JOEL ORDAZ
Reinforced Concrete Frame 8/26/2024 Approved JOEL ORDAZ
Reinforced Concrete Frame 9/11/2024 Approved JOEL ORDAZ
Reinforced Masonry Frame 9/11/2024 Approved JOEL ORDAZ
Footing/Foundation/Slab 9/18/2024 Approved JOEL ORDAZ
Wood Frame 12/30/2024 Approved JOEL ORDAZ
Final 5/6/2025 Permit Finaled JOEL ORDAZ
SGSOV-Seismic Gas S/O Valve 5/6/2025 SGSOV Approved JOEL ORDAZ
Smoke Detectors 5/6/2025 Approved JOEL ORDAZ