13778 W DESMOND ST 91331
Certificate Information: 13778 W DESMOND ST 91331
- Application / Permit
- 22016-20000-34461
- Plan Check / Job No.
- B22VN16852
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (N) 16'-0" x 24'-0" ATTACHED PATIO COVER TO (E) S.F.D. PER INFORMATION BULLETIN P/BC 2020-006, FIRE DAMAGE REPAIR TO FRAMING LESS THAN 10% OF REPLACEMENT COST, INTERIOR REMODEL TO REPLACE DRYWALL, ADD CLOSETS, RELOCATE BATHROOM DOOR, REMOVE NON-BEARING WALL.
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2022 | ANTOAN MISHRIKI |
| Corrections Issued | 11/14/2022 | ANTOAN MISHRIKI |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 2/9/2023 | MICHEL ABAJAN |
| Permit Finaled | 2/10/2023 | RONALD MYRICK |
| CofO Issued | 2/10/2023 | RONALD MYRICK |
| Permit Finaled | 2/10/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/15/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 11/15/2022 | LEE GUILBEAUX |
| Public Works-Sewers | Cleared | 11/15/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Vicsinc.Com; Lic. No.: 1002544-B | P O BOX 950931 MISSION HILLS, CA 91395 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/23/2022 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/30/2022 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 11/30/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 11/30/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 12/2/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 12/2/2022 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/2/2022 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 12/8/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/3/2023 | Approved | MICHEL ABAJAN |
| Final | 2/3/2023 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 2/3/2023 | Approved | MICHEL ABAJAN |
| METHANE-Final | 2/3/2023 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 2/3/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/3/2023 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2023 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 2/3/2023 | Approved | MICHEL ABAJAN |
| Wood Frame | 2/3/2023 | Approved | MICHEL ABAJAN |
| Final | 2/9/2023 | OK to Issue CofO | MICHEL ABAJAN |