12338 N BRADLEY AVE 91342

Certificate Information: 12338 N BRADLEY AVE 91342

Application / Permit
22016-20000-34374
Plan Check / Job No.
B22VN16800
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: (N) 20' x 20' DETACHED ADU PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)1, (d)1, and (g). WORK PER WFPP.
Permit Issued
Issued on 7/1/2023
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/18/2022 APPLICANT
Assigned to Plan Check Engineer 11/23/2022 GURUNATH NESARAJAH
Corrections Issued 11/24/2022 GURUNATH NESARAJAH
Plan Check Approved 6/26/2023 ISIS ARGUETA
Issued 7/1/2023 APPLICANT
CofO in Progress 4/6/2026 JENNIFER RABUCHIN
Permit Finaled 5/14/2026 RUBEN SALAS
CofO Issued 5/14/2026 RUBEN SALAS
Permit Finaled 5/14/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/12/2022 MEGAN GODINEZ
Construction near power lines Cleared 3/5/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 6/7/2023 MEGAN GODINEZ
Roof/Waste drainage to street Cleared 6/22/2023 DAGOVERTO GUERRERO
Sewer availability Cleared 6/22/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/5/2023 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 3/7/2024 Partial Approval KEVIN BERBERYAN
PLUMBING-Rough 6/4/2024 Conditional Approval JOSE AVILA
PLUMBING-Rough 8/22/2024 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 9/9/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 9/11/2024 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/20/2024 Partial Approval LOUIS ESCOTO
BUILDING-Rough-Frame 3/10/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 3/10/2025 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 3/10/2025 Approved JENNIFER RABUCHIN
Green Building Rough 3/10/2025 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 3/10/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/17/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/17/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 3/17/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 3/17/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/27/2025 Corrections Issued JENNIFER RABUCHIN
Insulation 3/27/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 4/3/2025 Approved JENNIFER RABUCHIN
Shower Pan 4/3/2025 Corrections Issued JENNIFER RABUCHIN
Shower Pan 5/7/2025 Corrections Issued JENNIFER RABUCHIN
Shower Pan 5/12/2025 Approved WILLIAM WREN
PLUMBING-Rough 6/9/2025 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 6/12/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 8/15/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 10/2/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/17/2026 Approved JENNIFER RABUCHIN
Final 2/17/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/17/2026 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 2/17/2026 Conditional Approval JENNIFER RABUCHIN
Smoke Detectors 2/17/2026 Approved JENNIFER RABUCHIN
Final 3/16/2026 OK to Issue CofO JENNIFER RABUCHIN
Service/Power Release 3/16/2026 Approved JENNIFER RABUCHIN