10215 N VASSAR AVE 91311
Certificate Information: 10215 N VASSAR AVE 91311
- Application / Permit
- 22016-20000-34271
- Plan Check / Job No.
- B22VN16762
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' 10" X 17' 8" DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). ALL WORK DONE PER WFPP. COMPLY WITH DEPARTMENT ORDER effective date 10/21/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
- Permit Issued
- Issued on 5/5/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2022 | JESSE ARELLANO |
| Corrections Issued | 11/15/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 12/16/2022 | APPLICANT |
| Applicant returned to address corrections | 4/20/2023 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 4/28/2023 | GURUNATH NESARAJAH |
| Issued | 5/5/2023 | APPLICANT |
| CofO in Progress | 1/4/2024 | MARK DOVICO |
| CofO Issued | 2/7/2024 | DAVID JAMES |
| Permit Finaled | 2/7/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 3/16/2023 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2023 | MEGAN GODINEZ |
| Sewer availability | Cleared | 3/16/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/9/2023 | Approved | MARK DOVICO |
| Deputy Drilled-In Anchors | 5/15/2023 | No Access for Inspection | MARK DOVICO |
| Footing/Foundation/Slab | 5/18/2023 | Approved | MARK DOVICO |
| BUILDING-Rough-Frame | 6/1/2023 | Corrections Issued | MARK DOVICO |
| Green Building Rough | 6/1/2023 | Corrections Issued | MARK DOVICO |
| HVAC-Final | 6/8/2023 | Approved | MARK DOVICO |
| BUILDING-Rough-Frame | 6/28/2023 | Approved | MARK DOVICO |
| Final | 6/28/2023 | Conditional Approval | MARK DOVICO |
| Green Building Final | 6/28/2023 | Approved | MARK DOVICO |
| Green Building Rough | 6/28/2023 | Approved | MARK DOVICO |
| SGSOV-Seismic Gas S/O Valve | 6/28/2023 | SGSOV Approved | MARK DOVICO |
| Smoke Detectors | 6/28/2023 | Approved | MARK DOVICO |