8809-8811 N TYRONE AVE 91402

Certificate Information: 8809-8811 N TYRONE AVE 91402

Application / Permit
22016-20000-34192
Plan Check / Job No.
B22VN16739
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). WORK PER ENGINEER.
Permit Issued
Issued on 12/20/2022
Issuing Office
Valley
Current Status
CofO Issued on 7/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/10/2022 APPLICANT
Assigned to Plan Check Engineer 11/14/2022 JESSE ARELLANO
Corrections Issued 11/14/2022 JESSE ARELLANO
Building Plans Picked Up 11/16/2022 APPLICANT
Plan Check Approved 12/20/2022 ROSENDO MEDINA
Issued 12/20/2022 APPLICANT
CofO in Progress 6/27/2023 GREGG CUMMINGS
Permit Finaled 7/21/2023 DANIEL ORRANTE
CofO Issued 7/21/2023 DANIEL ORRANTE
Permit Finaled 7/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/18/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/18/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 11/18/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/20/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 1/23/2023 Conditional Approval CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 2/9/2023 Conditional Approval CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 2/15/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 2/15/2023 Approved GREGG CUMMINGS
PLUMBING-Rough 2/15/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 2/27/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 2/27/2023 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/3/2023 Partial Approval GREGG CUMMINGS
ELECTRICAL-Rough 3/3/2023 Approved GREGG CUMMINGS
Green Building Rough 3/3/2023 Approved GREGG CUMMINGS
HVAC-Rough 3/3/2023 Approved GREGG CUMMINGS
Pre-Inspection 3/10/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 3/14/2023 Corrections Issued CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/20/2023 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 3/20/2023 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 3/30/2023 Approved WILLIAM WREN
Interior/Exterior Lathing 3/30/2023 Approved WILLIAM WREN
Shower Pan 4/4/2023 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 4/10/2023 Partial Approval GREGG CUMMINGS
Shower Pan 4/10/2023 Approved GREGG CUMMINGS
Final 5/26/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 5/26/2023 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 5/26/2023 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 6/9/2023 Approved GREGG CUMMINGS
Final 6/9/2023 Not Ready for Inspection GREGG CUMMINGS
HVAC-Final 6/9/2023 Approved GREGG CUMMINGS
PLUMBING-Final 6/9/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/9/2023 SGSOV Approved GREGG CUMMINGS
Final 6/27/2023 OK to Issue CofO GREGG CUMMINGS