14002 W VALLEYHEART DR 91423
Certificate Information: 14002 W VALLEYHEART DR 91423
- Application / Permit
- 22016-20000-33788
- Plan Check / Job No.
- B22VN16589
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 20' X 20' DETACHED GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER WFPP AND ENGINEERED DETAIL.
- Permit Issued
- Issued on 2/6/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 11/11/2022 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 11/14/2022 | APPLICANT |
| Applicant returned to address corrections | 12/6/2022 | HAYATO TSUCHIYA |
| Issued | 2/6/2023 | APPLICANT |
| CofO in Progress | 8/4/2023 | MISAEL ESPARZA |
| Permit Finaled | 9/6/2023 | RUBEN SALAS |
| CofO Issued | 9/6/2023 | RUBEN SALAS |
| Permit Finaled | 9/6/2023 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 11/14/2022 | MIGUEL GAMBOA |
| Address approval | Cleared | 11/15/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 11/15/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2022 | MEGAN GODINEZ |
| Public Works-Highway Ded. | Cleared | 11/16/2022 | MEGAN GODINEZ |
| Public Works-Open Permits | Cleared | 11/16/2022 | MEGAN GODINEZ |
| Public Works-Sewers | Cleared | 11/16/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 2/2/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Dlr Contractors; Lic. No.: 1066743-B | 14950 SAN JOSE ST MISSION HILLS, CA 91345 |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/9/2023 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/10/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 3/10/2023 | Partial Approval | MISAEL ESPARZA |
| Rough-Elec/Plmb/HVAC | 4/7/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/19/2023 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 4/19/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 4/19/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/25/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/1/2023 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 5/1/2023 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 5/1/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/5/2023 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 5/5/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Insulation | 5/10/2023 | Approved | THOMAS FINNILA |
| Interior/Exterior Lathing | 5/10/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/12/2023 | Partial Approval | THOMAS FINNILA |
| Green Building Rough | 5/12/2023 | Not Ready for Inspection | THOMAS FINNILA |
| MERV13>=Rough | 5/12/2023 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 5/19/2023 | Approved | ROBERT GOLD |
| Green Building Rough | 5/19/2023 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 5/19/2023 | Partial Approval | ROBERT GOLD |
| MERV13>=Rough | 5/19/2023 | Approved | ROBERT GOLD |
| Drywall Nailing | 5/24/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/1/2023 | Approved | DAVID ANDERSON |
| Shower Pan | 6/6/2023 | Approved | THOMAS FINNILA |
| Underground Mechanical | 6/6/2023 | Partial Approval | THOMAS FINNILA |
| Final | 7/21/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 7/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Final | 7/21/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/21/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 7/21/2023 | Partial Approval | MISAEL ESPARZA |
| Final | 7/26/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 8/3/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 8/3/2023 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 8/3/2023 | Approved | MISAEL ESPARZA |