2419 3/4 W VERNON AVE 90008
Certificate Information: 2419 3/4 W VERNON AVE 90008
- Application / Permit
- 22016-20000-33777
- Plan Check / Job No.
- B22VN16579
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DET. GARAGE TO NEW ACCESSORY DWELLING UNIT (20' x 36') PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) [ADU B]
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Current Status
- CofO Issued on 2/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | SEAN SHAHMIRI |
| Corrections Issued | 11/14/2022 | SEAN SHAHMIRI |
| Quality Review Completed | 11/16/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 11/18/2022 | APPLICANT |
| Applicant returned to address corrections | 2/6/2023 | SEAN SHAHMIRI |
| Plan Check Approved | 2/6/2023 | SEAN SHAHMIRI |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 2/5/2024 | ANTHONY EGSON |
| Permit Finaled | 2/19/2024 | DEROLD HAUFF |
| CofO Issued | 2/19/2024 | DEROLD HAUFF |
| Permit Finaled | 2/19/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2022 | WALLIE JONG |
| Sewer availability | Cleared | 12/1/2022 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2022 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 12/9/2022 | KURT CORRAL |
| Community Plan Implem. Overlay | Cleared | 2/2/2023 | KYLE WINSTON |
| Miscellaneous | Cleared | 2/2/2023 | KYLE WINSTON |
Contact Information
| Architect | Mcvay,, Bruce Cameron; Lic. No.: C11870 | 6440 E. EL ROBLE STREET LONG BEACH, CA 90815 |
| Contractor | Rent Ready Construction Inc; Lic. No.: 1065376-B | 631 N SIERRA BONITA AVE LOS ANGELES, CA 90036 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/16/2023 | Partial Approval | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 4/10/2023 | Approved | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/10/2023 | Conditional Approval | MICHAEL LEWIS |
| Footing/Foundation/Slab | 4/21/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/26/2023 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 5/5/2023 | Approved | ANTHONY EGSON |
| Sewer | 5/15/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 5/15/2023 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 5/15/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Corrections Issued | ANTHONY EGSON |
| Wood Frame | 8/7/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 8/9/2023 | Approved | ANTHONY EGSON |
| Deputy Wood Construction | 8/9/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | ANTHONY EGSON |
| Wood Frame | 8/10/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2023 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 8/24/2023 | Corrections Issued | STUART CHAPMAN |
| Deputy Drilled-In Anchors | 8/30/2023 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 9/27/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/27/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 9/27/2023 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 9/27/2023 | Approved | ANTHONY EGSON |
| Wood Frame | 9/27/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/2/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 10/3/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 10/3/2023 | Approved | ANTHONY EGSON |
| Wood Frame | 10/13/2023 | Partial Approval | ANTHONY EGSON |
| Insulation | 10/17/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 11/8/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 11/8/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/17/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 1/17/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 1/17/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 1/17/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 1/17/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 1/17/2024 | Approved | ANTHONY EGSON |
| HVAC-Final | 1/17/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 1/17/2024 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 1/17/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 1/22/2024 | Corrections Issued | ANTHONY EGSON |
| Smoke Detectors | 1/23/2024 | Approved | ANTHONY EGSON |
| Final | 2/5/2024 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 2/5/2024 | Approved | ANTHONY EGSON |