12925-12927 W LOUVRE ST 91331

Certificate Information: 12925-12927 W LOUVRE ST 91331

Application / Permit
22016-20000-33673
Plan Check / Job No.
B22VN16522
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO JUNIOR ACCESSORY DWELLING UNIT (443 SQ FT) PER GCS 65852.2(e)(1)(A) and 65852.22. CONVERT LAUNDRY ROOM TO BATHROOM. ALL WORK PER WFPP.
Permit Issued
Issued on 3/14/2023
Issuing Office
Current Status
CofO Issued on 12/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 JEROME MAGAT PALMA
Corrections Issued 11/12/2022 JEROME MAGAT PALMA
Applicant returned to address corrections 1/18/2023 JEROME MAGAT PALMA
Applicant returned to address corrections 2/4/2023 JEROME MAGAT PALMA
Applicant returned to address corrections 2/24/2023 LUISANGEL VALENZUELA
Plan Check Approved 3/3/2023 LUISANGEL VALENZUELA
Issued 3/14/2023 APPLICANT
CofO in Progress 10/13/2023 MICHEL ABAJAN
CofO Issued 12/21/2023 RUBEN SALAS
Permit Finaled 12/21/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/5/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 12/5/2022 COLIN LOREDO
Sewer availability Cleared 12/5/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/5/2023 Partial Inspection MICHEL ABAJAN
Footing/Foundation/Slab 5/15/2023 Not Ready for Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 5/19/2023 Conditional Approval ROBERT GOLD
Deputy Drilled-In Anchors 5/22/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 5/23/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 5/23/2023 Partial Approval MICHEL ABAJAN
Sewer 5/23/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/6/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Rough 6/6/2023 Approved MICHEL ABAJAN
Green Building Rough 6/6/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 6/6/2023 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 6/6/2023 Corrections Issued MICHEL ABAJAN
BUILDING-Rough-Frame 6/14/2023 Partial Inspection ROBERT GOLD
Green Building Rough 6/14/2023 Not Ready for Inspection ROBERT GOLD
HVAC-Rough 6/14/2023 Not Ready for Inspection ROBERT GOLD
PLUMBING-Rough 6/14/2023 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 6/21/2023 Approved MICHEL ABAJAN
Green Building Rough 6/21/2023 Approved MICHEL ABAJAN
HVAC-Rough 6/21/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 6/21/2023 Approved MICHEL ABAJAN
Insulation 6/28/2023 Corrections Issued WILLIAM WREN
Interior/Exterior Lathing 6/28/2023 Approved WILLIAM WREN
Insulation 7/5/2023 Approved MICHEL ABAJAN
Drywall Nailing 7/12/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 7/25/2023 Approved MICHEL ABAJAN
Shower Pan 7/25/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 10/13/2023 Approved MICHEL ABAJAN
Final 10/13/2023 OK to Issue CofO MICHEL ABAJAN
Green Building Final 10/13/2023 Approved MICHEL ABAJAN
HVAC-Final 10/13/2023 Approved MICHEL ABAJAN
PLUMBING-Final 10/13/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/13/2023 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 10/13/2023 Approved MICHEL ABAJAN