231 1/2 E 85TH ST 90003

Certificate Information: 231 1/2 E 85TH ST 90003

Application / Permit
22016-20000-33643
Plan Check / Job No.
B22VN16508
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN : CONVERT (E) GARAGES TO A.D.U. PER CA Govt. Code 65852.2(e)(1)(A). 2ND FLOOR OF BUILDING IS EXISTING SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/17/2023
Issuing Office
Current Status
CofO Issued on 8/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/8/2022 APPLICANT
Assigned to Plan Check Engineer 11/15/2022 EDWIN ESPIN
Corrections Issued 11/17/2022 EDWIN ESPIN
Plan Check Approved 1/5/2023 ANDREW SANTIAGO
Issued 1/17/2023 APPLICANT
CofO in Progress 8/17/2023 STUART CHAPMAN
Permit Finaled 8/21/2023 DEROLD HAUFF
CofO Issued 8/21/2023 DEROLD HAUFF
Permit Finaled 8/21/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/27/2022 AMAAN MALIK
Sewer availability Cleared 12/27/2022 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/30/2022 AMAAN MALIK

Contact Information

Contractor Jme General Construction Inc; Lic. No.: 924662-B       ,
Engineer Samadzadeh,, Hooman Ali; Lic. No.: NA87661       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/19/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 3/3/2023 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 3/3/2023 Approved LILIANA PORTILLO
ELECTRICAL-Rough 3/20/2023 Conditional Approval LILIANA PORTILLO
HVAC-Rough 3/20/2023 Not Ready for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 3/20/2023 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 3/20/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 3/24/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 3/24/2023 Approved LILIANA PORTILLO
Wood Frame 3/30/2023 Corrections Issued LILIANA PORTILLO
Wood Frame 4/3/2023 Corrections Issued JOAQUIN GREENOUGH
BUILDING-Rough-Frame 4/11/2023 Approved LILIANA PORTILLO
Green Building Rough 4/11/2023 Approved LILIANA PORTILLO
Insulation 4/13/2023 Approved LILIANA PORTILLO
Drywall Nailing 4/24/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 4/24/2023 Approved LILIANA PORTILLO
Sewer 4/24/2023 Approved LILIANA PORTILLO
Underground Mechanical 4/24/2023 Approved LILIANA PORTILLO
Final 6/16/2023 Corrections Issued MICHAEL LEWIS
Green Building Final 6/16/2023 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 6/16/2023 SGSOV Approved MICHAEL LEWIS
Smoke Detectors 6/16/2023 Approved MICHAEL LEWIS
Final 6/22/2023 Corrections Issued STUART CHAPMAN
Final 8/8/2023 Conditional Approval MICHAEL LEWIS
ELECTRICAL-Final 8/17/2023 Approved STUART CHAPMAN
Final 8/17/2023 OK to Issue CofO STUART CHAPMAN
HVAC-Final 8/17/2023 Approved STUART CHAPMAN
PLUMBING-Final 8/17/2023 Approved STUART CHAPMAN
Service/Power Release 8/17/2023 Approved STUART CHAPMAN