19936-19938 W HATTON ST 91306

Certificate Information: 19936-19938 W HATTON ST 91306

Application / Permit
22016-20000-33630
Plan Check / Job No.
B22VN16500
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EX ATTACHED 2-CAR GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (e). ALL WORK PER WFPP.
Permit Issued
Issued on 12/12/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 SERGIO MUNIZ
Corrections Issued 11/9/2022 SERGIO MUNIZ
Building Plans Picked Up 11/18/2022 APPLICANT
Issued 12/12/2022 APPLICANT
CofO in Progress 3/8/2024 ARUTYUN MADATYAN
Permit Finaled 3/21/2024 JOHN JANSON
CofO Issued 3/21/2024 JOHN JANSON
Permit Finaled 3/21/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/23/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/23/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 11/23/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/27/2023 Approved ALEXANDER HANDY
Pre-Inspection 9/26/2023 Corrections Issued ALEXANDER HANDY
PLUMBING-Rough 10/6/2023 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 10/11/2023 Partial Approval DAVID SCANTLIN
Deputy Drilled-In Anchors 10/17/2023 Conditional Approval ALEXANDER HANDY
Footing/Foundation/Slab 10/20/2023 Approved ALEXANDER HANDY
ELECTRICAL-Rough 11/27/2023 Corrections Issued ALEXANDER HANDY
HVAC-Rough 11/27/2023 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 11/27/2023 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 12/21/2023 Corrections Issued ALEXANDER HANDY
ELECTRICAL-Rough 12/21/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 12/21/2023 Approved ALEXANDER HANDY
PLUMBING-Rough 12/21/2023 Approved ALEXANDER HANDY
ELECTRICAL-Rough 12/29/2023 Not Ready for Inspection ALEXANDER HANDY
Footing/Foundation/Slab 12/29/2023 Not Ready for Inspection ALEXANDER HANDY
BUILDING-Rough-Frame 1/22/2024 Approved ALEXANDER HANDY
Green Building Rough 1/22/2024 Approved ALEXANDER HANDY
Insulation 1/29/2024 Approved ALEXANDER HANDY
Drywall Nailing 1/31/2024 Approved ALEXANDER HANDY
Final 2/26/2024 Corrections Issued ARUTYUN MADATYAN
Green Building Final 2/26/2024 Not Ready for Inspection ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 2/26/2024 SGSOV Not Ready ARUTYUN MADATYAN
Smoke Detectors 2/26/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 3/7/2024 Approved ARUTYUN MADATYAN
Final 3/7/2024 OK to Issue CofO ARUTYUN MADATYAN
Green Building Final 3/7/2024 Approved ARUTYUN MADATYAN
HVAC-Final 3/7/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 3/7/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 3/7/2024 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 3/7/2024 Approved ARUTYUN MADATYAN