7876 N VAN NUYS BLVD 91402
Certificate Information: 7876 N VAN NUYS BLVD 91402
- Application / Permit
- 22016-20000-33502
- Plan Check / Job No.
- B22VN16409
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (21) Theater
- Work Description
- Eplan Interior tenant improvement to a movie theatre including modified stadium seating within 16 auditoriums for new recliner seating.
- Permit Issued
- Issued on 3/15/2023
- Issuing Office
- Current Status
- Permit Finaled on 7/12/2023
Permit Application Status History
| Submitted | 11/3/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2022 | ARSALAN SHABESTARI |
| Corrections Issued | 12/8/2022 | ARSALAN SHABESTARI |
| Quality Review Completed | 12/9/2022 | GARO TELMI |
| Applicant returned to address corrections | 3/14/2023 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/15/2023 | ARSALAN SHABESTARI |
| Issued | 3/15/2023 | SHANNON HAAS |
| Permit Finaled | 7/12/2023 | STEVEN LEVITT |
Permit Application Clearance Information
| Green Code | Cleared | 1/24/2023 | MICHAEL AYERS |
| DAS Clearance | Cleared | 2/13/2023 | Samuel Gonzalez |
| Fire Marshal Fire Life Safety | Cleared | 3/10/2023 | MENOA AGHAJANI |
Contact Information
| Contractor | Galaxy Builders Group Inc; Lic. No.: 726654-B | , |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Reinforced Concrete Frame | 3/17/2023 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 3/20/2023 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 3/22/2023 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 5/8/2023 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 5/8/2023 | Partial Inspection | ANDREW DORSO |
| Deputy Reinf. Concrete | 5/10/2023 | Conditional Approval | ANDREW DORSO |
| Final | 5/18/2023 | Partial Inspection | ANDREW DORSO |
| Green Building Final | 5/18/2023 | Not Ready for Inspection | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 5/18/2023 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 5/18/2023 | Corrections Issued | ANDREW DORSO |
| Special/Order Compliance | 5/18/2023 | Partial Approval | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 5/26/2023 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 5/26/2023 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 6/12/2023 | Approved | ANDREW DORSO |
| Deputy Drilled-In Anchors | 7/11/2023 | Conditional Approval | ANDREW DORSO |
| Final | 7/12/2023 | Permit Finaled | STEVEN LEVITT |
| Green Building Final | 7/12/2023 | Approved | STEVEN LEVITT |
| Smoke Detectors | 7/12/2023 | Approved | STEVEN LEVITT |