680 N BROOKTREE ROAD 90402

Certificate Information: 680 N BROOKTREE ROAD 90402

Application / Permit
22016-20000-33368
Plan Check / Job No.
B22VN16324
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Add 3'-8" x 7'-6" and install skylight to expand (e) bathroom and (n) 3'-9" x 7'-6" trellis area per engineer. "COMPLY WITH DEPARTMENT ORDER effective date 05/10/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 12/22/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/2/2022 APPLICANT
Assigned to Plan Check Engineer 11/2/2022 MOHAMMAD ESMAILI
Corrections Issued 11/2/2022 MOHAMMAD ESMAILI
Plan Check Approved 12/20/2022 ANGELICA MARTINEZ
Issued 12/22/2022 APPLICANT
Permit Finaled 3/12/2024 BRUCE TODD
CofO Issued 3/12/2024 BRUCE TODD
Permit Finaled 3/12/2024 BRUCE TODD

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Kappe,, Ron H; Lic. No.: C18457 801 D STREET      SAN RAFAEL, CA 94901
Contractor Bradley Custom Carpentry Inc; Lic. No.: 826428-B 929 HILTS AVENUE      LOS ANGELES, CA 90024
Engineer Parker,, Leo Augustine; Lic. No.: S2829 1927 PONTIUS AVE      LOS ANGELES, CA 90025

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/21/2023 Approved RYAN BARNES
BUILDING-Rough-Frame 4/5/2023 Corrections Issued JOHN MATTILLO
ELECTRICAL-Rough 4/5/2023 Approved JOHN MATTILLO
FLOOD-Proofing Certificate 4/5/2023 Approved JOHN MATTILLO
Green Building Rough 4/5/2023 Approved JOHN MATTILLO
HVAC-Rough 4/5/2023 Approved JOHN MATTILLO
PLUMBING-Rough 4/5/2023 Approved JOHN MATTILLO
BUILDING-Rough-Frame 4/27/2023 Approved ANDREW BEELI
Drywall Nailing 5/15/2023 Approved JOHN MATTILLO
PLUMBING-Rough 5/15/2023 Approved JOHN MATTILLO
Interior/Exterior Lathing 5/18/2023 Approved JOHN MATTILLO
ELECTRICAL-Final 11/1/2023 Corrections Issued ANDREW BEELI
Final 11/1/2023 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 11/1/2023 Approved ANDREW BEELI
Green Building Final 11/1/2023 Not Ready for Inspection ANDREW BEELI
HVAC-Final 11/1/2023 Not Ready for Inspection ANDREW BEELI
PLUMBING-Final 11/1/2023 Corrections Issued ANDREW BEELI
Smoke Detectors 11/1/2023 Approved ANDREW BEELI
ELECTRICAL-Final 1/18/2024 Approved JOHN MATTILLO
Final 1/18/2024 Corrections Issued JOHN MATTILLO
Green Building Final 1/18/2024 Approved JOHN MATTILLO
HVAC-Final 1/18/2024 Approved JOHN MATTILLO
PLUMBING-Final 1/18/2024 Approved JOHN MATTILLO
Final 3/7/2024 Conditional Approval JOHN MATTILLO