4703 N WILLOW CREST AVE 91602

Certificate Information: 4703 N WILLOW CREST AVE 91602

Application / Permit
22016-20000-33298
Plan Check / Job No.
B22VN16284
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE 18' 3" X 3' 9" PORTION OF (E) DETACHED GARAGE, ADD 18' 3" X 3' 9" TO (E) DETACHED GARAGE AND CONVERT GARAGE TO ACCESSORY DWELLING UNIT AND ADD 2ND STORY LOFT ABOVE PER LAMC 12.22 A.33 (c) AND (d). ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 2/21/2023
Issuing Office
Current Status
CofO Issued on 5/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/10/2022 LUISANGEL VALENZUELA
Corrections Issued 11/11/2022 LUISANGEL VALENZUELA
Applicant returned to address corrections 1/24/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/9/2023 GURUNATH NESARAJAH
Plan Check Approved 2/17/2023 GURUNATH NESARAJAH
Issued 2/21/2023 APPLICANT
CofO in Progress 5/14/2025 JAVIER RAMOS JR
Permit Finaled 5/29/2025 RUBEN SALAS
CofO Issued 5/29/2025 RUBEN SALAS
Permit Finaled 5/29/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/2/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/2/2022 LEE GUILBEAUX
Sewer availability Cleared 12/2/2022 LEE GUILBEAUX

Contact Information

Contractor Eagle Custom Works Inc; Lic. No.: 993343-B       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVENUE      LONG BEACH, CA 90813

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/13/2023 Approved RYAN SALAZAR
PLUMBING-Rough 10/19/2023 Partial Approval CHRISTOPHE COCHRAN
Sewer 10/19/2023 Approved CHRISTOPHE COCHRAN
Wood Frame 11/14/2023 Corrections Issued JOHN COLEMAN
BUILDING-Rough-Frame 11/20/2023 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 11/20/2023 Approved JOHN COLEMAN
Green Building Rough 11/20/2023 Not Ready for Inspection JOHN COLEMAN
HVAC-Rough 11/20/2023 Not Ready for Inspection JOHN COLEMAN
Interior/Exterior Lathing 11/20/2023 Not Ready for Inspection JOHN COLEMAN
MERV13>=Rough 11/20/2023 Not Ready for Inspection JOHN COLEMAN
PLUMBING-Rough 11/20/2023 Approved JOHN COLEMAN
Rough-Elec/Plmb/HVAC 11/20/2023 Not Ready for Inspection JOHN COLEMAN
Shower Pan 11/20/2023 Not Ready for Inspection JOHN COLEMAN
BUILDING-Rough-Frame 1/22/2024 Corrections Issued JAVIER RAMOS JR
Green Building Rough 1/22/2024 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 1/22/2024 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 1/22/2024 Partial Approval JAVIER RAMOS JR
MERV13>=Rough 1/22/2024 Approved JAVIER RAMOS JR
Pre-Inspection 1/22/2024 Approved JAVIER RAMOS JR
Shower Pan 1/22/2024 Corrections Issued JAVIER RAMOS JR
Insulation 1/25/2024 Approved RYAN SALAZAR
Shower Pan 1/25/2024 Approved RYAN SALAZAR
Special/Order Compliance 1/25/2024 Corrections Issued RYAN SALAZAR
Drywall Nailing 2/2/2024 Approved CRAIG DAVIS
Interior/Exterior Lathing 2/2/2024 Approved CRAIG DAVIS
Service/Power Release 2/2/2024 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 6/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 6/7/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 6/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Rough 6/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
MERV13>=Final 6/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 6/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Smoke Detectors 6/7/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 11/8/2024 Partial Inspection CHRISTOPHER ROJAS
Final 11/8/2024 Partial Inspection CHRISTOPHER ROJAS
Green Building Final 11/8/2024 Partial Inspection CHRISTOPHER ROJAS
Green Building Rough 11/8/2024 Partial Inspection CHRISTOPHER ROJAS
MERV13>=Final 11/8/2024 Partial Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 11/8/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 11/8/2024 Partial Inspection CHRISTOPHER ROJAS
Smoke Detectors 11/8/2024 Partial Inspection CHRISTOPHER ROJAS
Final 11/12/2024 Corrections Issued CHRISTOPHER ROJAS
Special/Order Compliance 11/12/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 11/15/2024 Partial Inspection CHRISTOPHER ROJAS
Green Building Rough 11/15/2024 Partial Inspection CHRISTOPHER ROJAS
HVAC-Rough 11/15/2024 Approved CHRISTOPHER ROJAS
Special/Order Compliance 11/15/2024 Partial Inspection JUAN VALENZUELA
Wood Frame 11/15/2024 Partial Inspection CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/29/2025 Approved CHRISTOPHER ROJAS
Final 1/29/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 1/29/2025 Approved CHRISTOPHER ROJAS
Green Building Rough 1/29/2025 Approved CHRISTOPHER ROJAS
MERV13>=Final 1/29/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 1/29/2025 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 1/29/2025 Approved CHRISTOPHER ROJAS
Final 3/5/2025 Partial Inspection CHRISTOPHER ROJAS
Service/Power Release 3/5/2025 Partial Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 5/13/2025 Approved JAVIER RAMOS JR
Final 5/13/2025 OK to Issue CofO JAVIER RAMOS JR
HVAC-Final 5/13/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 5/13/2025 Approved JAVIER RAMOS JR
Service/Power Release 5/13/2025 Approved JAVIER RAMOS JR