12610 W MARTHA ST 91607

Certificate Information: 12610 W MARTHA ST 91607

Application / Permit
22016-20000-33227
Plan Check / Job No.
B22VN16250
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE INTO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 12/14/2022
Issuing Office
Current Status
CofO Issued on 5/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2022 APPLICANT
Assigned to Plan Check Engineer 11/7/2022 AMY GUEVARRA
Corrections Issued 11/8/2022 EDWIN ESPIN
Applicant returned to address corrections 11/18/2022 JASON JANGADA
Applicant returned to address corrections 11/18/2022 HANS SANTIAGO
Applicant returned to address corrections 11/29/2022 AMY GUEVARRA
Plan Check Approved 12/14/2022 FARSHAD ALIMOHAMADI
Issued 12/14/2022 APPLICANT
CofO in Progress 5/15/2023 KIRK SANDERS
CofO Issued 5/15/2023 MICHAEL SMITH
Permit Finaled 5/15/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/9/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 11/9/2022 COLIN LOREDO
Sewer availability Cleared 11/9/2022 COLIN LOREDO

Contact Information

Contractor Excel Construction L A Inc; Lic. No.: 998499-B       ,
Contractor Excel Construction La Inc; Lic. No.: 998499-B       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/19/2022 Partial Approval KIRK SANDERS
Footing/Foundation/Slab 12/19/2022 Approved KIRK SANDERS
Green Building Rough 12/19/2022 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 12/19/2022 Approved KIRK SANDERS
BUILDING-Rough-Frame 1/18/2023 Not Ready for Inspection KIRK SANDERS
Green Building Rough 1/18/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 1/25/2023 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 1/25/2023 Not Ready for Inspection KIRK SANDERS
Green Building Rough 1/25/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Rough 1/25/2023 Not Ready for Inspection KIRK SANDERS
Interior/Exterior Lathing 1/25/2023 Approved KIRK SANDERS
PLUMBING-Rough 1/25/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 1/30/2023 Approved KIRK SANDERS
Deputy Drilled-In Anchors 1/30/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 1/30/2023 Approved KIRK SANDERS
Green Building Rough 1/30/2023 Approved KIRK SANDERS
HVAC-Rough 1/30/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 1/30/2023 Approved KIRK SANDERS
Shower Pan 1/30/2023 Approved KIRK SANDERS
Insulation 2/1/2023 Corrections Issued KIRK SANDERS
Insulation 2/3/2023 Approved KIRK SANDERS
Drywall Nailing 2/7/2023 Partial Approval KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 2/7/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 2/9/2023 Approved MISAEL ESPARZA
Drywall Nailing 3/21/2023 Approved KIRK SANDERS
ELECTRICAL-Final 3/21/2023 Corrections Issued KIRK SANDERS
Final 3/21/2023 Corrections Issued KIRK SANDERS
Green Building Final 3/21/2023 Not Ready for Inspection KIRK SANDERS
HVAC-Final 3/21/2023 Corrections Issued KIRK SANDERS
PLUMBING-Final 3/21/2023 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/21/2023 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 3/21/2023 Approved KIRK SANDERS
ELECTRICAL-Final 3/31/2023 Corrections Issued KIRK SANDERS
Final 3/31/2023 Not Ready for Inspection KIRK SANDERS
Green Building Final 3/31/2023 Approved KIRK SANDERS
HVAC-Final 3/31/2023 Approved KIRK SANDERS
PLUMBING-Final 3/31/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Approved KIRK SANDERS
ELECTRICAL-Final 4/24/2023 Corrections Issued KIRK SANDERS
Final 4/24/2023 Corrections Issued KIRK SANDERS
HVAC-Final 4/24/2023 Approved KIRK SANDERS
PLUMBING-Final 4/24/2023 Approved KIRK SANDERS
ELECTRICAL-Final 5/12/2023 Approved KIRK SANDERS
Final 5/12/2023 OK to Issue CofO KIRK SANDERS
HVAC-Final 5/12/2023 Approved KIRK SANDERS
PLUMBING-Final 5/12/2023 Approved KIRK SANDERS