11730 N VERADA AVE 91344
Certificate Information: 11730 N VERADA AVE 91344
- Application / Permit
- 22016-20000-32969
- Plan Check / Job No.
- B22VN16113
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Converting existing Garage and 2nd Floor Recreation Room to New Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/6/2023
- Issuing Office
- Current Status
- CofO Issued on 10/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/31/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2022 | HANS SANTIAGO |
| Corrections Issued | 11/4/2022 | HANS SANTIAGO |
| Plan Check Approved | 12/31/2022 | ANDREW SANTIAGO |
| Issued | 1/6/2023 | APPLICANT |
| CofO in Progress | 10/8/2025 | STEVEN BACK |
| Permit Finaled | 10/15/2025 | JOHN JANSON |
| CofO Issued | 10/15/2025 | JOHN JANSON |
| Permit Finaled | 10/15/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/7/2022 | ROMAN GUTIERREZ |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2022 | ROMAN GUTIERREZ |
| Grading Pre-Inspection | Cleared | 11/15/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 11/15/2022 | ROMAN GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/4/2024 | Partial Inspection | STEVEN BACK |
| Deputy Drilled-In Anchors | 5/28/2024 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 6/4/2024 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 6/7/2024 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 6/28/2024 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 6/28/2024 | Approved | STEVEN BACK |
| Special/Order Compliance | 7/11/2024 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 9/13/2024 | Corrections Issued | STEVEN BACK |
| Sewer | 9/13/2024 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 9/20/2024 | Approved | JEFFREY PARD |
| Sewer | 9/20/2024 | Not Ready for Inspection | JEFFREY PARD |
| ELECTRICAL-Rough | 10/25/2024 | Approved | STEVEN BACK |
| HVAC-Rough | 10/25/2024 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 11/1/2024 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Approved | STEVEN BACK |
| Insulation | 11/1/2024 | Approved | STEVEN BACK |
| Underground Mechanical | 11/27/2024 | Partial Approval | JEFFREY PARD |
| Underground Mechanical | 12/6/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 1/9/2025 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 2/7/2025 | Approved | STEVEN BACK |
| Shower Pan | 2/7/2025 | Approved | STEVEN BACK |
| Final | 10/3/2025 | Corrections Issued | JEFFREY PARD |
| METHANE-Final | 10/3/2025 | Approved | JEFFREY PARD |
| SGSOV-Seismic Gas S/O Valve | 10/3/2025 | SGSOV Not Ready | JEFFREY PARD |
| Smoke Detectors | 10/3/2025 | Approved | JEFFREY PARD |
| ELECTRICAL-Final | 10/8/2025 | Approved | STEVEN BACK |
| Final | 10/8/2025 | OK to Issue CofO | STEVEN BACK |
| HVAC-Final | 10/8/2025 | Approved | STEVEN BACK |
| PLUMBING-Final | 10/8/2025 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/8/2025 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 10/8/2025 | Approved | STEVEN BACK |