11730 N VERADA AVE 91344

Certificate Information: 11730 N VERADA AVE 91344

Application / Permit
22016-20000-32969
Plan Check / Job No.
B22VN16113
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan Converting existing Garage and 2nd Floor Recreation Room to New Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 1/6/2023
Issuing Office
Current Status
CofO Issued on 10/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/31/2022 APPLICANT
Assigned to Plan Check Engineer 11/4/2022 HANS SANTIAGO
Corrections Issued 11/4/2022 HANS SANTIAGO
Plan Check Approved 12/31/2022 ANDREW SANTIAGO
Issued 1/6/2023 APPLICANT
CofO in Progress 10/8/2025 STEVEN BACK
Permit Finaled 10/15/2025 JOHN JANSON
CofO Issued 10/15/2025 JOHN JANSON
Permit Finaled 10/15/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/7/2022 ROMAN GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 11/15/2022 ROMAN GUTIERREZ
Grading Pre-Inspection Cleared 11/15/2022 KIRK LINKLATER
Sewer availability Cleared 11/15/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/4/2024 Partial Inspection STEVEN BACK
Deputy Drilled-In Anchors 5/28/2024 Conditional Approval HENRY KIM
Footing/Foundation/Slab 6/4/2024 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 6/7/2024 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 6/28/2024 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 6/28/2024 Approved STEVEN BACK
Special/Order Compliance 7/11/2024 Partial Approval STEVEN BACK
PLUMBING-Rough 9/13/2024 Corrections Issued STEVEN BACK
Sewer 9/13/2024 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 9/20/2024 Approved JEFFREY PARD
Sewer 9/20/2024 Not Ready for Inspection JEFFREY PARD
ELECTRICAL-Rough 10/25/2024 Approved STEVEN BACK
HVAC-Rough 10/25/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 11/1/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Approved STEVEN BACK
Insulation 11/1/2024 Approved STEVEN BACK
Underground Mechanical 11/27/2024 Partial Approval JEFFREY PARD
Underground Mechanical 12/6/2024 Partial Approval CHRIS CHRISTENSEN
Drywall Nailing 1/9/2025 Approved STEVEN BACK
Interior/Exterior Lathing 2/7/2025 Approved STEVEN BACK
Shower Pan 2/7/2025 Approved STEVEN BACK
Final 10/3/2025 Corrections Issued JEFFREY PARD
METHANE-Final 10/3/2025 Approved JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 10/3/2025 SGSOV Not Ready JEFFREY PARD
Smoke Detectors 10/3/2025 Approved JEFFREY PARD
ELECTRICAL-Final 10/8/2025 Approved STEVEN BACK
Final 10/8/2025 OK to Issue CofO STEVEN BACK
HVAC-Final 10/8/2025 Approved STEVEN BACK
PLUMBING-Final 10/8/2025 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 10/8/2025 SGSOV Approved STEVEN BACK
Service/Power Release 10/8/2025 Approved STEVEN BACK