7922 S TRUXTON AVE 90045

Certificate Information: 7922 S TRUXTON AVE 90045

Application / Permit
22016-20000-32887
Plan Check / Job No.
B22VN16057
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL TO THE (E) KITCHEN, MASTER BATHROOM & CLOSET, REMVE LOAD-BEARING WAL BETWEEN KITCHEN/LIVING ROOM, RELOCATE LAUNDRY, CONVERT (1) CLOSET TO MUD ROOM, REPLACE WINDOWS & DOORS AND RAISE MASTER BEDROOM CEILING. ALL WORK DONE PER ENGINEERING.
Permit Issued
Issued on 11/10/2022
Issuing Office
Valley
Current Status
Permit Finaled on 1/26/2025

Permit Application Status History

Submitted 10/28/2022 APPLICANT
Assigned to Plan Check Engineer 10/28/2022 GURUNATH NESARAJAH
Corrections Issued 10/28/2022 GURUNATH NESARAJAH
Plan Check Approved 11/10/2022 GURUNATH NESARAJAH
Issued 11/10/2022 APPLICANT
Permit Finaled 1/24/2025 TEMISTOCLES CAAL

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/11/2023 Approved BOBBY KEY
Special/Order Compliance 1/11/2023 Corrections Issued BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/13/2023 Corrections Issued CLAYTON GRAHAM
Wood Frame 1/13/2023 Not Ready for Inspection CLAYTON GRAHAM
Insulation 1/23/2023 Partial Approval BOBBY KEY
Wood Frame 1/23/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 3/1/2023 Not Ready for Inspection HERBERT GIRON
Footing/Foundation/Slab 3/1/2023 Approved HERBERT GIRON
HVAC-Rough 3/2/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 3/6/2023 Corrections Issued BOBBY KEY
HVAC-Rough 3/6/2023 Approved BOBBY KEY
PLUMBING-Rough 3/6/2023 Approved BOBBY KEY
Wood Frame 3/6/2023 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 3/10/2023 Conditional Approval BOBBY KEY
Interior/Exterior Lathing 3/10/2023 Partial Approval BOBBY KEY
Shower Pan 3/10/2023 Approved BOBBY KEY
Interior/Exterior Lathing 3/15/2023 Conditional Approval HERBERT GIRON
Wood Frame 3/15/2023 Not Ready for Inspection HERBERT GIRON
Interior/Exterior Lathing 3/21/2023 Approved BOBBY KEY
Wood Frame 3/21/2023 Approved BOBBY KEY
Insulation 3/22/2023 Corrections Issued JESUS RODRIGUEZ
Drywall Nailing 4/4/2023 Approved BOBBY KEY
Insulation 4/4/2023 Approved BOBBY KEY
ELECTRICAL-Final 10/16/2023 Corrections Issued BOBBY KEY
Final 10/16/2023 Not Ready for Inspection BOBBY KEY
HVAC-Final 10/16/2023 Corrections Issued BOBBY KEY
PLUMBING-Final 10/16/2023 Corrections Issued BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Not Ready BOBBY KEY
Smoke Detectors 10/16/2023 Approved BOBBY KEY
Deputy Drilled-In Anchors 11/2/2023 Conditional Approval BOBBY KEY
Final 11/27/2024 No Access for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 11/27/2024 SGSOV Not Ready BOBBY KEY
Final 1/24/2025 Permit Finaled TEMISTOCLES CAAL
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Approved TEMISTOCLES CAAL