948 1/4-1/2 W 59TH DR 90044
Certificate Information: 948 1/4-1/2 W 59TH DR 90044
- Application / Permit
- 22016-20000-32847
- Plan Check / Job No.
- B22VN16049
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan - convert (e) 4-car garage in 2-story accessory building to 1 attached ADU and 1 JADU
- Permit Issued
- Issued on 5/26/2023
- Issuing Office
- Current Status
- CofO Issued on 6/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | KELVIN CHUONG |
| Corrections Issued | 12/2/2022 | KELVIN CHUONG |
| Quality Review Completed | 12/8/2022 | RODOLFO ARIAS |
| Applicant returned to address corrections | 3/10/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 4/25/2023 | KELVIN CHUONG |
| Applicant returned to address corrections | 5/18/2023 | KELVIN CHUONG |
| Plan Check Approved | 5/24/2023 | KELVIN CHUONG |
| Issued | 5/26/2023 | APPLICANT |
| CofO in Progress | 4/22/2025 | BARRY HACHE |
| No Progress | 4/27/2025 | DEROLD HAUFF |
| CofO in Progress | 4/27/2025 | DEROLD HAUFF |
| Permit Finaled | 6/13/2025 | DEROLD HAUFF |
| Permit Finaled | 6/13/2025 | DEROLD HAUFF |
| CofO Issued | 6/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 12/7/2022 | MICHAEL SOTO |
| Address approval | Cleared | 12/12/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 12/12/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2023 | AMAAN MALIK |
| Miscellaneous | Cleared | 4/14/2023 | MARITZA PRZEKOP |
| SB8 RUD | Cleared | 5/1/2023 | JESSICA WANG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/26/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 8/8/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 8/8/2023 | Approved | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 8/15/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 8/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Sewer | 8/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/15/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 8/29/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 9/5/2023 | Partial Approval | BRENDAN MORELLI |
| Deputy Drilled-In Anchors | 9/11/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/27/2023 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Rough | 10/27/2023 | Corrections Issued | CRAIG DAVIS |
| Gas Test | 10/27/2023 | Corrections Issued | CRAIG DAVIS |
| HVAC-Rough | 10/27/2023 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 10/27/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Wood Frame | 10/27/2023 | Not Ready for Inspection | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/15/2023 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 11/15/2023 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 11/15/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 11/15/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 12/22/2023 | Approved | CRAIG DAVIS |
| Wood Frame | 12/22/2023 | Approved | CRAIG DAVIS |
| Insulation | 1/4/2024 | Approved | JUSTIN HAWLEY |
| Wood Frame | 1/4/2024 | Corrections Issued | JUSTIN HAWLEY |
| Deputy Wood Construction | 1/11/2024 | Conditional Approval | DAVID FEILER |
| Drywall Nailing | 1/17/2024 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 1/17/2024 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 1/23/2024 | Not Ready for Inspection | JOSE MACIAS |
| Drywall Nailing | 1/29/2024 | Approved | JOSE MACIAS |
| Interior/Exterior Lathing | 1/29/2024 | Conditional Approval | JOSE MACIAS |
| Underground Mechanical | 1/22/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Final | 2/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 2/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 2/19/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 2/19/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 2/19/2025 | Approved | NICHOLAS LOPEZ |
| Final | 3/11/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Final | 3/11/2025 | Corrections Issued | BARRY HACHE |
| Final | 3/17/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 4/8/2025 | Corrections Issued | BARRY HACHE |
| Final | 4/17/2025 | Corrections Issued | BARRY HACHE |
| Final | 4/21/2025 | OK to Issue CofO | BARRY HACHE |