11961 N GERALD AVE 91344

Certificate Information: 11961 N GERALD AVE 91344

Application / Permit
22016-20000-32727
Plan Check / Job No.
B22VN15987
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF (N) 17'-10" x 7'-9 1/2" AND INTERIOR REMODEL TO (E) KITCHEN TO (E) S.F.D. PER ENGINEERING
Permit Issued
Issued on 12/9/2022
Issuing Office
Valley
Current Status
CofO Issued on 9/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 RAMA DABADGE
Corrections Issued 10/27/2022 RAMA DABADGE
Plan Check Approved 12/1/2022 ALFRED RAMIREZ
Issued 12/9/2022 APPLICANT
CofO in Progress 8/11/2023 RAUL OLAGI
Permit Finaled 9/6/2023 RUBEN SALAS
CofO Issued 9/6/2023 RUBEN SALAS
Permit Finaled 9/6/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/27/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/27/2022 LEE GUILBEAUX
Grading Pre-Inspection Cleared 11/1/2022 LANNY MERRICK

Contact Information

Contractor Owner-Builder       ,
Engineer Khanjian,, Hovik J; Lic. No.: C51609 326 S. SPARKS STREET      BURBANK, CA 91506

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/10/2023 Partial Approval JAVIER RAMOS JR
Deputy Drilled-In Anchors 2/15/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 2/15/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/3/2023 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 3/3/2023 Approved JAVIER RAMOS JR
Green Building Rough 3/3/2023 Approved JAVIER RAMOS JR
HVAC-Rough 3/3/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 3/3/2023 Approved JAVIER RAMOS JR
Drywall Nailing 3/6/2023 Approved CHRISTOPHER DELLEFIELD
Insulation 3/6/2023 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 3/6/2023 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/14/2023 Approved JAVIER RAMOS JR
Final 7/14/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 7/14/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 7/14/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 7/14/2023 Approved JAVIER RAMOS JR
Final 8/11/2023 OK to Issue CofO RAUL OLAGI