10581 W MAHONEY DR 91040
Certificate Information: 10581 W MAHONEY DR 91040
- Application / Permit
- 22016-20000-32451
- Plan Check / Job No.
- B22VN15877
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT 11' X 20' 8" PORTION OF (E) ATTACHED GARAGE TO BEDROOM/BATHROOM, RELOCATE KITCHEN, RECONFIGURE FLOOR PLAN AND RELOCATE LAUNDRY ROOM. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 12/19/2022
- Issuing Office
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2022 | LUISANGEL VALENZUELA |
| Corrections Issued | 11/2/2022 | LUISANGEL VALENZUELA |
| Plan Check Approved | 11/22/2022 | GURUNATH NESARAJAH |
| Issued | 12/19/2022 | APPLICANT |
| CofO in Progress | 2/24/2024 | DAVID ANDERSON |
| Permit Finaled | 4/18/2024 | RUBEN SALAS |
| CofO Issued | 4/18/2024 | RUBEN SALAS |
| Permit Finaled | 4/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 11/2/2022 | COLIN LOREDO |
| ZI | Cleared | 11/9/2022 | CECILIA CASTILLO |
Contact Information
| Contractor | B & G Homes Inc; Lic. No.: 912819-B | , |
| Engineer | Espino,, Manuel A; Lic. No.: NA55526 | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/21/2022 | Partial Inspection | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 1/12/2023 | Conditional Approval | MICHAEL SMITH |
| PLUMBING-Rough | 1/13/2023 | Partial Approval | DAVID ANDERSON |
| Sewer | 1/13/2023 | Partial Approval | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 1/25/2023 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 1/25/2023 | Approved | DAVID ANDERSON |
| Sewer | 3/22/2023 | Approved | DAVID ANDERSON |
| Wood Frame | 3/30/2023 | Partial Approval | DAVID ANDERSON |
| Deputy Wood Construction | 3/31/2023 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Approved | DAVID ANDERSON |
| Deputy Steel/Welding | 4/21/2023 | Conditional Approval | ROBERT GOLD |
| PLUMBING-Rough | 4/27/2023 | Approved | DAVID ANDERSON |
| Structural Steel Frame | 4/27/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 5/5/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 5/18/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 5/18/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 5/18/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/18/2023 | Approved | DAVID ANDERSON |
| Insulation | 5/30/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 5/30/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Shower Pan | 5/30/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 6/9/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 6/9/2023 | Partial Approval | DAVID ANDERSON |
| Final | 2/6/2024 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 2/6/2024 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/6/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 2/6/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 2/14/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Green Building Final | 2/14/2024 | Approved | DAVID ANDERSON |
| Smoke Detectors | 2/14/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 2/20/2024 | Conditional Approval | DAVID ANDERSON |
| Final | 2/20/2024 | OK to Issue CofO | DAVID ANDERSON |
| Smoke Detectors | 2/20/2024 | Approved | DAVID ANDERSON |