16330 W NORDHOFF ST 91343

Certificate Information: 16330 W NORDHOFF ST 91343

Application / Permit
22016-20000-32159
Plan Check / Job No.
B22VN15738
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE AND RECREATION ROOM TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 2/6/2023
Issuing Office
Current Status
CofO Issued on 8/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 DANIEL YIP
Corrections Issued 10/28/2022 DANIEL YIP
Applicant returned to address corrections 11/10/2022 DANIEL YIP
Plan Check Approved 2/4/2023 DANIEL YIP
Issued 2/6/2023 APPLICANT
CofO in Progress 8/14/2023 RAUL OLAGI
Permit Finaled 8/28/2023 RUBEN SALAS
CofO Issued 8/28/2023 RUBEN SALAS
Permit Finaled 8/28/2023 RUBEN SALAS

Permit Application Clearance Information

Construction near power lines Cleared 10/31/2022 WALTER RAMIREZ
Address approval Cleared 11/2/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 11/8/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 1/10/2023 JOHN LIN
Miscellaneous Cleared 2/4/2023 DANIEL YIP

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2023 Approved RAUL OLAGI
PLUMBING-Rough 2/23/2023 Corrections Issued RAUL OLAGI
Sewer 2/23/2023 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 2/28/2023 Partial Approval RAUL OLAGI
Sewer 2/28/2023 Approved RAUL OLAGI
Footing/Foundation/Slab 3/29/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 5/15/2023 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 5/15/2023 Corrections Issued RAUL OLAGI
HVAC-Rough 5/15/2023 Corrections Issued RAUL OLAGI
PLUMBING-Rough 5/15/2023 Corrections Issued RAUL OLAGI
Underground Mechanical 5/15/2023 Partial Approval RAUL OLAGI
BUILDING-Rough-Frame 6/5/2023 Partial Approval RAUL OLAGI
Interior/Exterior Lathing 6/5/2023 Partial Approval RAUL OLAGI
Rough-Elec/Plmb/HVAC 6/5/2023 Approved RAUL OLAGI
Insulation 6/7/2023 Approved RAUL OLAGI
BUILDING-Rough-Frame 6/13/2023 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/13/2023 Approved CHRISTOPHE COCHRAN
Shower Pan 6/13/2023 Approved CHRISTOPHE COCHRAN
Drywall Nailing 6/23/2023 Approved RAUL OLAGI
Final 8/8/2023 Corrections Issued RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Approved RAUL OLAGI
Smoke Detectors 8/8/2023 Approved RAUL OLAGI
Final 8/14/2023 OK to Issue CofO RAUL OLAGI