3308 N NORTH KNOLL DR 90068
Certificate Information: 3308 N NORTH KNOLL DR 90068
- Application / Permit
- 22016-20000-32095
- Plan Check / Job No.
- B22VN15718
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MODIFY 3-STORY ELEVATOR HOIST WAY FOR AN ELEVATOR INSTALLATION
- Permit Issued
- Issued on 12/20/2022
- Issuing Office
- Valley
- Current Status
- Issued on 12/20/2022
Permit Application Status History
| Submitted | 10/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | SELLA BENYAMIN |
| Corrections Issued | 11/17/2022 | SELLA BENYAMIN |
| Quality Review Completed | 11/30/2022 | STEVEN KIM |
| Building Plans Picked Up | 12/1/2022 | APPLICANT |
| Plan Check Approved | 12/20/2022 | SELLA BENYAMIN |
| Issued | 12/20/2022 | APPLICANT |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Mulick Construction And Design Inc; Lic. No.: 372231-B | 1476 DORSET AVENUE THOUSAND OAKS, CA 91360 |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 3/7/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Wood Frame | 3/7/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 3/14/2023 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 3/16/2023 | Partial Approval | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 3/17/2023 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/10/2023 | Approved | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 4/11/2023 | Conditional Approval | BRIAN SULLIVAN |
| Deputy Drilled-In Anchors | 4/18/2023 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 4/21/2023 | Approved | BRIAN SULLIVAN |
| Insulation | 4/21/2023 | Approved | BRIAN SULLIVAN |
| Wood Frame | 4/21/2023 | Approved | BRIAN SULLIVAN |
| Deputy Reinf. Concrete | 4/25/2023 | Conditional Approval | BRIAN SULLIVAN |
| Drywall Nailing | 5/1/2023 | Approved | BRIAN SULLIVAN |
| Final | 5/4/2023 | Corrections Issued | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 5/4/2023 | SGSOV Approved | BRIAN SULLIVAN |
| Smoke Detectors | 5/4/2023 | Approved | BRIAN SULLIVAN |
| Final | 3/18/2024 | Not Ready for Inspection | ROY SPAULDING |