10700 N BALBOA BLVD 103 91344
Certificate Information: 10700 N BALBOA BLVD 103 91344
- Application / Permit
- 22016-20000-31909
- Plan Check / Job No.
- B22VN15626
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- CHANGE OF USE FROM (E) 64'8" X 25' RETAIL TO MEDICAL OFFICE , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 1/3/2023
- Issuing Office
- Valley
- Current Status
- Issued on 1/3/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/20/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2022 | RARES BODEA |
| Disabled Access Plans Picked Up | 11/15/2022 | APPLICANT |
| Corrections Issued | 11/21/2022 | RARES BODEA |
| Quality Review Completed | 11/30/2022 | STEVEN KIM |
| Building Plans Picked Up | 12/1/2022 | APPLICANT |
| Plan Check Approved | 1/3/2023 | RARES BODEA |
| Issued | 1/3/2023 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 12/9/2022 | NORLITO MEDRANO |
| Miscellaneous | Cleared | 12/13/2022 | CLAUDIA RODRIGUEZ |
| Miscellaneous | Cleared | 12/13/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 12/13/2022 | MIGUEL GAMBOA |
| Specific Plan | Cleared | 12/14/2022 | CLAUDIA RODRIGUEZ |
| ZA Case | Cleared | 12/14/2022 | MIGUEL GAMBOA |
| ZI | Cleared | 12/14/2022 | CLAUDIA RODRIGUEZ |
| Comm Cor/Mini-Mall | Cleared | 12/27/2022 | STEVEN WECHSLER |
| Eng Process Fee Ord 176,300 | Cleared | 12/30/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 12/30/2022 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 12/30/2022 | LEE GUILBEAUX |
Contact Information
| Contractor | Artisana Inc; Lic. No.: 523361-B | 150 S GLENOAKS BLVD PMB 9365 BURBANK, CA 91510 |
| Engineer | Taroian,, Armen; Lic. No.: C78011 | 411 PALM DR APT 204 GLENDALE, CA 91202 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/20/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 1/23/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 2/2/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 2/16/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 3/7/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Light Gage Steel Frame | 3/21/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 3/29/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Final | 7/20/2023 | Partial Inspection | DEANDRE HOFFMAN |
| SGSOV-Seismic Gas S/O Valve | 7/20/2023 | SGSOV Approved | DEANDRE HOFFMAN |
| Smoke Detectors | 7/20/2023 | Approved | DEANDRE HOFFMAN |
| Wood Frame | 7/20/2023 | Approved | DEANDRE HOFFMAN |