1546 1/2 S HAUSER BLVD 90019

Certificate Information: 1546 1/2 S HAUSER BLVD 90019

Application / Permit
22016-20000-31705
Plan Check / Job No.
B22VN15557
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX. DETACHED GARAGE/STORAGE AND ENCLOSE PATIO COVER INTO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). WITH ALL NEW ROOF FRAMING. WORK PER ENGINEER.
Permit Issued
Issued on 3/1/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/21/2022 HAYATO TSUCHIYA
Corrections Issued 10/22/2022 HAYATO TSUCHIYA
Building Plans Picked Up 10/24/2022 APPLICANT
Plan Check Approved 3/1/2023 ROSENDO MEDINA
Issued 3/1/2023 APPLICANT
CofO in Progress 1/9/2024 RONNIE MINDANAO
CofO Issued 1/21/2024 DEROLD HAUFF
Permit Finaled 1/21/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/31/2023 AMAAN MALIK
Roof/Waste drainage to street Cleared 1/31/2023 AMAAN MALIK
Sewer availability Cleared 1/31/2023 AMAAN MALIK
Construction near power lines Cleared 2/3/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/15/2023 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Mejia,, Fernando Finuliar; Lic. No.: C54382 8305 DUCOR AVE      WEST HILLS, CA 91304

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/15/2023 Approved JOSE AVILA
Footing/Foundation/Slab 6/21/2023 Approved SCOTT FINNILA
Sewer 6/21/2023 Approved SCOTT FINNILA
BUILDING-Rough-Frame 7/12/2023 Corrections Issued JOSE AVILA
METHANE-Rough 7/12/2023 Approved JOSE AVILA
PLUMBING-Rough 7/18/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 8/10/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/10/2023 Approved JOSE AVILA
HVAC-Rough 8/10/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 8/25/2023 Approved JOSE AVILA
ELECTRICAL-Rough 8/25/2023 Approved JOSE AVILA
Green Building Rough 8/25/2023 Approved JOSE AVILA
HVAC-Rough 8/25/2023 Approved JOSE AVILA
Interior/Exterior Lathing 8/25/2023 Approved JOSE AVILA
PLUMBING-Rough 8/25/2023 Approved JOSE AVILA
Insulation 8/30/2023 Approved ROBERT CORNELL
Interior/Exterior Lathing 8/30/2023 Approved ROBERT CORNELL
Drywall Nailing 9/6/2023 Corrections Issued RONNIE MINDANAO
Drywall Nailing 9/13/2023 Approved JOSH MEISTER
ELECTRICAL-Rough 12/1/2023 Corrections Issued LILIANA PORTILLO
Final 12/26/2023 Corrections Issued SCOTT FINNILA
Green Building Final 12/26/2023 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 12/26/2023 SGSOV Not Ready SCOTT FINNILA
Smoke Detectors 12/26/2023 Approved SCOTT FINNILA
ELECTRICAL-Final 1/5/2024 Approved RONNIE MINDANAO
Final 1/5/2024 OK to Issue CofO RONNIE MINDANAO
HVAC-Final 1/5/2024 Approved RONNIE MINDANAO
PLUMBING-Final 1/5/2024 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 1/5/2024 SGSOV Approved RONNIE MINDANAO