8829 N SYLMAR AVE 91402

Certificate Information: 8829 N SYLMAR AVE 91402

Application / Permit
22016-20000-31475
Plan Check / Job No.
B22VN15451
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) 20' x 18' garage into detached one story ADU per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 12/6/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/21/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2022 APPLICANT
Assigned to Plan Check Engineer 10/19/2022 RAMA DABADGE
Corrections Issued 10/19/2022 RAMA DABADGE
Building Plans Picked Up 10/21/2022 APPLICANT
Plan Check Approved 12/6/2022 ISIS ARGUETA
Issued 12/6/2022 APPLICANT
CofO in Progress 1/25/2024 GREGG CUMMINGS
Permit Finaled 2/21/2024 RUBEN SALAS
CofO Issued 2/21/2024 RUBEN SALAS
Permit Finaled 2/21/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 11/23/2022 FERNANDO GIL
Roof/Waste drainage to street Cleared 11/23/2022 FERNANDO GIL
Sewer availability Cleared 11/23/2022 FERNANDO GIL
Eng Process Fee Ord 176,300 Cleared 11/28/2022 FERNANDO GIL
Construction near power lines Cleared 12/5/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 4/3/2023 Approved CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/12/2023 Corrections Issued GREGG CUMMINGS
Underground Mechanical 4/12/2023 Corrections Issued GREGG CUMMINGS
Deputy Drilled-In Anchors 4/24/2023 Conditional Approval MICHAEL SMITH
PLUMBING-Rough 4/25/2023 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 5/1/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 5/4/2023 Conditional Approval CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 6/6/2023 Conditional Approval MICHAEL SMITH
BUILDING-Rough-Frame 6/12/2023 Corrections Issued GREGG CUMMINGS
Green Building Rough 6/12/2023 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 6/21/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 7/11/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 8/23/2023 Corrections Issued GREGG CUMMINGS
HVAC-Rough 8/23/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 8/23/2023 Approved GREGG CUMMINGS
ELECTRICAL-Rough 8/30/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 9/13/2023 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 10/4/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 10/10/2023 Approved GREGG CUMMINGS
Green Building Rough 10/10/2023 Approved GREGG CUMMINGS
HVAC-Rough 10/10/2023 Approved GREGG CUMMINGS
Insulation 10/19/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 10/19/2023 Not Ready for Inspection GREGG CUMMINGS
Interior/Exterior Lathing 10/25/2023 Partial Approval JUAN VALENZUELA
Drywall Nailing 11/9/2023 Approved DAVID ANDERSON
Final 12/27/2023 Corrections Issued GREGG CUMMINGS
Green Building Final 12/27/2023 Approved GREGG CUMMINGS
Pre-Inspection 12/27/2023 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 12/27/2023 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 12/27/2023 Approved GREGG CUMMINGS
Final 1/2/2024 Corrections Issued CHRISTOPHE COCHRAN
Final 1/9/2024 Corrections Issued GREGG CUMMINGS
Final 1/16/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 1/24/2024 Approved GREGG CUMMINGS
Final 1/24/2024 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 1/24/2024 Approved GREGG CUMMINGS
PLUMBING-Final 1/24/2024 Approved GREGG CUMMINGS