6610 N FARRALONE AVE 91303
Certificate Information: 6610 N FARRALONE AVE 91303
- Application / Permit
- 22016-20000-31302
- Plan Check / Job No.
- B22VN15405
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing garage to master bedroom and add new carport
- Permit Issued
- Issued on 11/28/2022
- Issuing Office
- Current Status
- Issued on 10/19/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/18/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2022 | JOSEPH RAFOLS |
| Corrections Issued | 10/24/2022 | JOSEPH RAFOLS |
| Plan Check Approved | 11/27/2022 | HERNAN ARREOLA |
| Issued | 11/28/2022 | APPLICANT |
| CofO in Progress | 10/19/2023 | TROY SANDERS |
| No Progress | 10/19/2023 | TROY SANDERS |
| CofO in Progress | 10/19/2023 | TROY SANDERS |
| No Progress | 10/19/2023 | TROY SANDERS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/27/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/27/2022 | CARLOS AGUILERA |
| ZI | Cleared | 10/28/2022 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 21126 MERRIDY STREET CHATSWORTH, CA 91311 |
| Engineer | Kazemi,, Milad; Lic. No.: NA92143 | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/11/2023 | Not Ready for Inspection | TROY SANDERS |
| Insulation | 1/11/2023 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 1/11/2023 | Not Ready for Inspection | TROY SANDERS |
| Wood Frame | 1/11/2023 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 3/14/2023 | Partial Approval | TROY SANDERS |
| Sewer | 3/14/2023 | Approved | TROY SANDERS |
| PLUMBING-Rough | 3/15/2023 | Partial Approval | TROY SANDERS |
| Sewer | 3/15/2023 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 3/17/2023 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/5/2023 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 7/21/2023 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 7/21/2023 | Approved | TROY SANDERS |
| Insulation | 7/21/2023 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 7/21/2023 | Approved | TROY SANDERS |
| Drywall Nailing | 8/8/2023 | Approved | TROY SANDERS |
| Insulation | 8/8/2023 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 8/8/2023 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 9/28/2023 | Approved | TROY SANDERS |
| Final | 9/28/2023 | Corrections Issued | TROY SANDERS |
| Green Building Final | 9/28/2023 | Not Ready for Inspection | TROY SANDERS |
| Green Building Rough | 9/28/2023 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 9/28/2023 | Approved | TROY SANDERS |
| Final | 10/19/2023 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 10/19/2023 | Approved | TROY SANDERS |