6610 N FARRALONE AVE 91303

Certificate Information: 6610 N FARRALONE AVE 91303

Application / Permit
22016-20000-31302
Plan Check / Job No.
B22VN15405
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing garage to master bedroom and add new carport
Permit Issued
Issued on 11/28/2022
Issuing Office
Current Status
Issued on 10/19/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/18/2022 APPLICANT
Assigned to Plan Check Engineer 10/21/2022 JOSEPH RAFOLS
Corrections Issued 10/24/2022 JOSEPH RAFOLS
Plan Check Approved 11/27/2022 HERNAN ARREOLA
Issued 11/28/2022 APPLICANT
CofO in Progress 10/19/2023 TROY SANDERS
No Progress 10/19/2023 TROY SANDERS
CofO in Progress 10/19/2023 TROY SANDERS
No Progress 10/19/2023 TROY SANDERS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/27/2022 CARLOS AGUILERA
Sewer availability Cleared 10/27/2022 CARLOS AGUILERA
ZI Cleared 10/28/2022 NELSON RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 10/31/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 21126 MERRIDY STREET      CHATSWORTH, CA 91311
Engineer Kazemi,, Milad; Lic. No.: NA92143       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/11/2023 Not Ready for Inspection TROY SANDERS
Insulation 1/11/2023 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 1/11/2023 Not Ready for Inspection TROY SANDERS
Wood Frame 1/11/2023 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 3/14/2023 Partial Approval TROY SANDERS
Sewer 3/14/2023 Approved TROY SANDERS
PLUMBING-Rough 3/15/2023 Partial Approval TROY SANDERS
Sewer 3/15/2023 Approved TROY SANDERS
Footing/Foundation/Slab 3/17/2023 Approved TROY SANDERS
BUILDING-Rough-Frame 5/5/2023 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 7/21/2023 Approved TROY SANDERS
ELECTRICAL-Rough 7/21/2023 Approved TROY SANDERS
Insulation 7/21/2023 Partial Approval TROY SANDERS
PLUMBING-Rough 7/21/2023 Approved TROY SANDERS
Drywall Nailing 8/8/2023 Approved TROY SANDERS
Insulation 8/8/2023 Approved TROY SANDERS
Interior/Exterior Lathing 8/8/2023 Partial Approval TROY SANDERS
BUILDING-Rough-Frame 9/28/2023 Approved TROY SANDERS
Final 9/28/2023 Corrections Issued TROY SANDERS
Green Building Final 9/28/2023 Not Ready for Inspection TROY SANDERS
Green Building Rough 9/28/2023 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Approved TROY SANDERS
Smoke Detectors 9/28/2023 Approved TROY SANDERS
Final 10/19/2023 OK to Issue CofO TROY SANDERS
Green Building Final 10/19/2023 Approved TROY SANDERS