7231 1/2 N KESTER AVE 91405

Certificate Information: 7231 1/2 N KESTER AVE 91405

Application / Permit
22016-20000-31180
Plan Check / Job No.
B22VN15343
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 12/12/2022
Issuing Office
Current Status
CofO Issued on 11/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2022 APPLICANT
Assigned to Plan Check Engineer 10/19/2022 DANIEL YIP
Corrections Issued 10/20/2022 DANIEL YIP
Plan Check Approved 11/16/2022 DANIEL YIP
Issued 12/12/2022 APPLICANT
CofO in Progress 10/25/2024 VINCENT HANLEY
Permit Finaled 11/2/2024 DANIEL ORRANTE
CofO Issued 11/2/2024 DANIEL ORRANTE
Permit Finaled 11/2/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/26/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 10/26/2022 LEE GUILBEAUX
Sewer availability Cleared 10/26/2022 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 10/26/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2023 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 8/10/2023 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 11/27/2023 Partial Approval GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 12/21/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 12/21/2023 Approved GREGG CUMMINGS
ELECTRICAL-Rough 2/21/2024 Approved GREGG CUMMINGS
HVAC-Rough 2/21/2024 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 2/21/2024 Corrections Issued GREGG CUMMINGS
Sewer 2/21/2024 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 3/12/2024 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 3/29/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 3/29/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 3/29/2024 Partial Approval KIRK SANDERS
PLUMBING-Rough 3/29/2024 Approved KIRK SANDERS
PLUMBING-Rough 4/23/2024 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Corrections Issued KIRK SANDERS
Insulation 5/1/2024 Approved KIRK SANDERS
Insulation 5/1/2024 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 5/1/2024 Corrections Issued KIRK SANDERS
Sewer 5/1/2024 Approved KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 5/8/2024 Approved KIRK SANDERS
BUILDING-Rough-Frame 5/10/2024 Approved KIRK SANDERS
Drywall Nailing 5/14/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/16/2024 Approved VINCENT HANLEY
Shower Pan 5/16/2024 Approved VINCENT HANLEY
Final 8/15/2024 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 8/15/2024 SGSOV Not Required VINCENT HANLEY
Smoke Detectors 8/15/2024 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 10/25/2024 Approved VINCENT HANLEY
Final 10/25/2024 OK to Issue CofO VINCENT HANLEY