1727 E 41ST PL BLDG-B 90058
Certificate Information: 1727 E 41ST PL BLDG-B 90058
- Application / Permit
- 22016-20000-31174
- Plan Check / Job No.
- B22VN14792
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Warehouse
- Work Description
- (eplan) Voluntary seismic retrofit of three existing buildings. No changes are proposed to the use, egress, occupancy, or square footages of the buildings. Proposed demolition or modification of the buildings and site will be limited to the extents required to accomplish the necessary structural upgrades and maintain accessible paths of travel.
- Permit Issued
- Issued on 5/2/2023
- Issuing Office
- Current Status
- Permit Finaled on 9/10/2024
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/6/2022 | YOUNG KIM |
| Corrections Issued | 10/13/2022 | YOUNG KIM |
| Quality Review Completed | 10/19/2022 | GARO TELMI |
| Applicant returned to address corrections | 12/21/2022 | YOUNG KIM |
| Applicant returned to address corrections | 1/9/2023 | YOUNG KIM |
| Applicant returned to address corrections | 1/18/2023 | YOUNG KIM |
| Applicant returned to address corrections | 1/25/2023 | YOUNG KIM |
| Applicant returned to address corrections | 2/16/2023 | YOUNG KIM |
| Applicant returned to address corrections | 3/9/2023 | YOUNG KIM |
| Applicant returned to address corrections | 4/13/2023 | YOUNG KIM |
| Applicant returned to address corrections | 4/17/2023 | YOUNG KIM |
| Plan Check Approved | 4/21/2023 | YOUNG KIM |
| Issued | 5/2/2023 | APPLICANT |
| Permit Finaled | 7/15/2024 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Green Code | Cleared | 1/25/2023 | MICHAEL AYERS |
| DAS Clearance | Cleared | 4/6/2023 | YOUNG KIM |
Contact Information
| Architect | The, Design Collaborative; Lic. No.: C36667 | 1745 E. 7TH ST. 1ST FLOOR LOS ANGELES, CA 90021 |
| Contractor | Charles Pankow Builders Ltd; Lic. No.: 688972-B | , |
| Engineer | Garza,, Jaime; Lic. No.: S5456 | 4022 BERENICE PLACE LOS ANGELES, CA 90031 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Grading | 6/7/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Pre-Inspection | 6/8/2023 | Approved | ALAN MORELOS |
| Footing/Foundation/Slab | 6/16/2023 | Partial Approval | ALAN MORELOS |
| Excavation/Setback/Form/Re-Bar | 7/21/2023 | Partial Approval | ALAN MORELOS |
| Wood Frame | 7/25/2023 | Corrections Issued | ALAN MORELOS |
| Deputy Reinf. Concrete | 8/9/2023 | Conditional Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 10/18/2023 | Approved | MARTIN TAVITIAN |
| Deputy Grading | 12/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Deputy Reinf. Concrete | 12/14/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2024 | Partial Approval | LUIS CCAMACHO |
| Final | 7/15/2024 | Permit Finaled | ALFREDO LOPEZ |
| Green Building Final | 7/15/2024 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/15/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 7/15/2024 | Approved | ALFREDO LOPEZ |