5428 N MORELLA AVE 91607

Certificate Information: 5428 N MORELLA AVE 91607

Application / Permit
22016-20000-31049
Plan Check / Job No.
B22VN15252
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan (E) 2-CAR GARAGE AND STORAGE TO BE CONVERTED TO ADU (APPX. 585 SF). all work to comply with engineering
Permit Issued
Issued on 8/3/2023
Issuing Office
Current Status
CofO Issued on 9/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2022 APPLICANT
Assigned to Plan Check Engineer 10/19/2022 JOSEPH RAFOLS
Corrections Issued 10/20/2022 JOSEPH RAFOLS
Plan Check Approved 2/27/2023 JOSEPH RAFOLS
Issued 8/3/2023 APPLICANT
CofO in Progress 9/13/2024 CHRISTOPHER ROJAS
CofO Issued 9/23/2024 DANIEL ORRANTE
Permit Finaled 9/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 11/14/2022 MEGAN GODINEZ
Sewer availability Cleared 11/14/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 11/17/2022 MEGAN GODINEZ
Public Works-Highway Ded. Cleared 11/17/2022 MEGAN GODINEZ
Public Works-Open Permits Cleared 11/17/2022 MEGAN GODINEZ
Public Works-Sewers Cleared 11/17/2022 MEGAN GODINEZ
Construction near power lines Cleared 2/11/2023 RIDWAN HARDY
Specific Plan Cleared 2/22/2023 CHRISTIAN PEARSON

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: NA78215       ,

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/18/2023 Corrections Issued THOMAS FINNILA
Deputy Drilled-In Anchors 8/25/2023 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 8/25/2023 Partial Approval JACK KARGODORIAN
Sewer 8/25/2023 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 9/5/2023 Partial Approval JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Approved RYAN SALAZAR
ELECTRICAL-Rough 9/22/2023 Approved JACK KARGODORIAN
PLUMBING-Rough 9/22/2023 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/4/2023 Corrections Issued THOMAS FINNILA
HVAC-Rough 10/4/2023 Partial Approval THOMAS FINNILA
Interior/Exterior Lathing 10/4/2023 Not Ready for Inspection THOMAS FINNILA
Interior/Exterior Lathing 10/10/2023 Partial Approval THOMAS FINNILA
Rough-Elec/Plmb/HVAC 10/10/2023 Approved THOMAS FINNILA
Shower Pan 10/10/2023 Approved THOMAS FINNILA
Wood Frame 10/10/2023 Approved THOMAS FINNILA
Insulation 10/18/2023 Corrections Issued CHRISTOPHER ROJAS
Insulation 10/23/2023 Approved JUAN VALENZUELA
Drywall Nailing 10/26/2023 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/20/2023 Approved RYAN SALAZAR
BUILDING-Rough-Frame 3/18/2024 Approved KIRK SANDERS
ELECTRICAL-Final 3/18/2024 Corrections Issued KIRK SANDERS
Final 3/18/2024 Corrections Issued KIRK SANDERS
Green Building Final 3/18/2024 Not Ready for Inspection KIRK SANDERS
Green Building Rough 3/18/2024 Approved KIRK SANDERS
HVAC-Final 3/18/2024 Corrections Issued KIRK SANDERS
MERV13>=Final 3/18/2024 Approved KIRK SANDERS
MERV13>=Rough 3/18/2024 Approved KIRK SANDERS
PLUMBING-Final 3/18/2024 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Approved KIRK SANDERS
Smoke Detectors 3/18/2024 Approved KIRK SANDERS
ELECTRICAL-Final 6/25/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Final 6/25/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Green Building Final 6/25/2024 Approved CHRISTOPHER ROJAS
HVAC-Final 6/25/2024 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 6/25/2024 Not Ready for Inspection CHRISTOPHER ROJAS
ELECTRICAL-Final 9/12/2024 Approved CHRISTOPHER ROJAS
Final 9/12/2024 OK to Issue CofO CHRISTOPHER ROJAS
HVAC-Final 9/12/2024 Approved CHRISTOPHER ROJAS
PLUMBING-Final 9/12/2024 Approved CHRISTOPHER ROJAS
Service/Power Release 9/12/2024 Approved CHRISTOPHER ROJAS