8810 N TAMPA AVE 91324

Certificate Information: 8810 N TAMPA AVE 91324

Application / Permit
22016-20000-30474
Plan Check / Job No.
B22VN15022
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
EPLAN: ADDITION AND TI: ADDITION (N) MEZZANINE FOR CONFERENCE AND OFFICE: 2,134 SF. TI: DEMOLISH EXISTING LOCKER ROOM WALLS, CASEWORK AND EQUIPMENT. CONSTRUCT NEW MEZZANINE LOCKER ROOM, WALLS, STAIRS, CASEWORK, AND EQUIPMENT. RELOCATE EXISTING EQUIPMENT. TI: Restaurant/Maet/Deli/Bakery on 03/14/2023
Permit Issued
Issued on 6/23/2023
Issuing Office
Current Status
CofO Issued on 12/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2022 APPLICANT
Assigned to Plan Check Engineer 10/27/2022 TSE MING HUANG
Corrections Issued 10/31/2022 TSE MING HUANG
Quality Review Completed 11/1/2022 EUGENE BARBEAU
Applicant returned to address corrections 5/4/2023 TSE MING HUANG
Plan Check Approved 6/20/2023 TSE MING HUANG
Issued 6/23/2023 APPLICANT
CofO in Progress 12/21/2023 JOHN KITCKO
Permit Finaled 12/21/2023 JEFFREY DURAN
CofO Issued 12/21/2023 JEFFREY DURAN
Permit Finaled 12/21/2023 JEFFREY DURAN

Permit Application Clearance Information

Metro Rail approval Cleared 11/22/2022 TSE MING HUANG
"Q" conditions Cleared 11/29/2022 NATHAN ROMINE
Miscellaneous Cleared 11/29/2022 NATHAN ROMINE
Miscellaneous Cleared 11/29/2022 NATHAN ROMINE
ZA Case Cleared 11/29/2022 NATHAN ROMINE
ZA Case Cleared 11/29/2022 NATHAN ROMINE
ZA Case Cleared 11/29/2022 NATHAN ROMINE
Eng Process Fee Ord 176,300 Cleared 12/20/2022 COLIN LOREDO
Sewer availability Cleared 12/20/2022 COLIN LOREDO
Green Code Cleared 2/7/2023 MICHAEL AYERS
DAS Clearance Cleared 5/5/2023 Gurunath Nesarajah

Contact Information

Architect Menard,, Nathan D; Lic. No.: C27019 345 W 6TH STREET UNIT A      TUSTIN, CA 92780
Contractor Harvey Usa Llc; Lic. No.: 866177-B       ,
Engineer Wampler,, Thomas Arthur; Lic. No.: S5334 19020 33RD AVE W STE 530      LYNNWOOD, WA 98036

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/17/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Drilled-In Anchors 7/18/2023 Conditional Approval DEANDRE HOFFMAN
Deputy Drilled-In Anchors 7/27/2023 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 7/31/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Drilled-In Anchors 8/7/2023 Conditional Approval DEANDRE HOFFMAN
Green Building Rough 8/11/2023 Partial Inspection DEANDRE HOFFMAN
Wood Frame 8/11/2023 Partial Inspection DEANDRE HOFFMAN
Light Gage Steel Frame 8/17/2023 Not Ready for Inspection DEANDRE HOFFMAN
Wood Frame 8/18/2023 Partial Inspection DEANDRE HOFFMAN
Green Building Rough 8/21/2023 Partial Inspection DEANDRE HOFFMAN
Deputy Wood Construction 8/23/2023 Conditional Approval DEANDRE HOFFMAN
Wood Frame 8/23/2023 Corrections Issued DEANDRE HOFFMAN
Green Building Rough 9/1/2023 Partial Inspection DEANDRE HOFFMAN
Wood Frame 9/1/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 9/11/2023 Partial Approval KENNETH ROBERTS
Green Building Rough 9/11/2023 Partial Approval KENNETH ROBERTS
Green Building Rough 9/14/2023 Partial Inspection DEANDRE HOFFMAN
Wood Frame 9/14/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 9/20/2023 Partial Inspection DEANDRE HOFFMAN
Green Building Rough 9/20/2023 Partial Inspection DEANDRE HOFFMAN
Partition/T-Bar Ceiling 10/3/2023 Partial Inspection DEANDRE HOFFMAN
Pre-Inspection 10/27/2023 Partial Inspection DEANDRE HOFFMAN
Drywall Nailing 11/27/2023 Not Ready for Inspection ROBERT DAVIS
Final 11/27/2023 Not Ready for Inspection ROBERT DAVIS
Green Building Final 11/27/2023 Not Ready for Inspection ROBERT DAVIS
Green Building Rough 11/27/2023 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 11/27/2023 Not Ready for Inspection ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Approved ROBERT DAVIS
Smoke Detectors 11/27/2023 Not Ready for Inspection ROBERT DAVIS
Wood Frame 11/27/2023 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 12/7/2023 Not Ready for Inspection STEVEN LEVITT
Final 12/7/2023 Not Ready for Inspection STEVEN LEVITT
Green Building Final 12/7/2023 Not Ready for Inspection STEVEN LEVITT
Green Building Rough 12/7/2023 Not Ready for Inspection STEVEN LEVITT
Reinforced Concrete Frame 12/7/2023 Not Ready for Inspection STEVEN LEVITT
Smoke Detectors 12/7/2023 Not Ready for Inspection STEVEN LEVITT
Wood Frame 12/7/2023 Not Ready for Inspection STEVEN LEVITT
Drywall Nailing 12/8/2023 Approved ROBERT DAVIS
Final 12/8/2023 Not Ready for Inspection ROBERT DAVIS
Green Building Final 12/8/2023 Approved ROBERT DAVIS
Green Building Rough 12/8/2023 Approved ROBERT DAVIS
Reinforced Concrete Frame 12/8/2023 Approved ROBERT DAVIS
Smoke Detectors 12/8/2023 Not Ready for Inspection ROBERT DAVIS
Wood Frame 12/8/2023 Approved ROBERT DAVIS
Final 12/15/2023 Not Ready for Inspection ROBERT DAVIS
Smoke Detectors 12/15/2023 Approved ROBERT DAVIS
Final 12/19/2023 Conditional Approval JOHN KITCKO
Final 12/21/2023 OK to Issue CofO JOHN KITCKO