4927 E LA CALANDRIA DR 90032
Certificate Information: 4927 E LA CALANDRIA DR 90032
- Application / Permit
- 22016-20000-30469
- Plan Check / Job No.
- B22VN15019
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTEND (E) DECK (4' X 33'-7") AT 1ST FLOOR OF (E) 2-STORY SFD W/ ATTACHED GARAGE
- Permit Issued
- Issued on 4/12/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 8/1/2024
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/27/2022 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/3/2022 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/4/2022 | STEVEN KIM |
| Building Plans Picked Up | 12/2/2022 | APPLICANT |
| Applicant returned to address corrections | 3/7/2023 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 1/26/2024 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 2/13/2024 | NILOOFAR MEHRAIN |
| Plan Check Approved | 3/12/2024 | NILOOFAR MEHRAIN |
| Issued | 4/12/2024 | APPLICANT |
| Permit Finaled | 7/31/2024 | LILIANA PORTILLO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/6/2022 | CELINA MORENO |
| "D" conditions | Cleared | 2/23/2023 | SPENCER WEJROWSKI |
| "Q" conditions | Cleared | 2/23/2023 | SPENCER WEJROWSKI |
| ZI | Cleared | 2/23/2023 | SPENCER WEJROWSKI |
| Grading Pre-Inspection | Cleared | 3/7/2023 | NILOOFAR MEHRAIN |
| Roof/Waste drainage to street | Cleared | 2/9/2024 | ARNULFO CHAMU |
Contact Information
| Contractor | Thynk Remodeling; Lic. No.: 1052597-B | 14622 VENTURA BLVD STE 326 LOS ANGELES, CA 91403 |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 6/6/2024 | Corrections Issued | LILIANA PORTILLO |
| Wood Frame | 6/14/2024 | Approved | LILIANA PORTILLO |
| Final | 7/10/2024 | Corrections Issued | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 7/10/2024 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 7/10/2024 | Corrections Issued | LILIANA PORTILLO |
| Final | 7/31/2024 | Permit Finaled | LILIANA PORTILLO |
| Smoke Detectors | 7/31/2024 | Approved | LILIANA PORTILLO |