6509 N AMIGO AVE 91335
Certificate Information: 6509 N AMIGO AVE 91335
- Application / Permit
- 22016-20000-30441
- Plan Check / Job No.
- B22VN15009
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 18'-0" x 20'-0" GARAGE TO AN ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 2/1/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/13/2022 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 10/14/2022 | MIROOSH KHACHATOORIAN |
| Building Plans Picked Up | 10/17/2022 | APPLICANT |
| Applicant returned to address corrections | 1/13/2023 | JESSE ARELLANO |
| Plan Check Approved | 1/19/2023 | ISIS ARGUETA |
| Issued | 2/1/2023 | APPLICANT |
| CofO in Progress | 5/19/2023 | JON MCHUGH |
| Permit Finaled | 5/30/2023 | JOHN JANSON |
| CofO Issued | 5/30/2023 | JOHN JANSON |
| Permit Finaled | 5/30/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/19/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2022 | CARLOS AGUILERA |
| ZI | Cleared | 10/20/2022 | DANG NGUYEN |
| Construction within easement | Cleared | 1/9/2023 | RIDWAN HARDY |
Contact Information
| Architect | Benavidez,, Alexis; Lic. No.: C39253 | 15948 DEVONSHIRE ST GRANADA HILLS, CA 91344 |
| Contractor | Build 4 You Inc; Lic. No.: 914440-B | 18740 OXNARD STREET #304 TARZANA, CA 91356 |
| Engineer | Van, Elden, Alexander Craig; Lic. No.: C71696 | 2415 FORDHAM DR COSTA MESA, CA 92626 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/7/2023 | Approved | SEAN HAUPT |
| Special/Order Compliance | 2/7/2023 | Corrections Issued | SEAN HAUPT |
| Deputy Drilled-In Anchors | 2/10/2023 | Conditional Approval | JON MCHUGH |
| Footing/Foundation/Slab | 2/15/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/21/2023 | Approved | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 3/21/2023 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 3/24/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 3/24/2023 | Approved | SEAN HAUPT |
| Insulation | 3/24/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 3/24/2023 | Approved | SEAN HAUPT |
| Shower Pan | 3/24/2023 | Approved | SEAN HAUPT |
| Drywall Nailing | 3/29/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 3/29/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2023 | Partial Approval | SEAN WIRCH |
| Sewer | 4/25/2023 | Approved | SEAN WIRCH |
| Final | 5/12/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Final | 5/12/2023 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 5/12/2023 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 5/12/2023 | Not Ready for Inspection | JON MCHUGH |
| Final | 5/15/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 5/15/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 5/15/2023 | SGSOV Not Required | JON MCHUGH |
| Smoke Detectors | 5/15/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 5/18/2023 | Approved | JON MCHUGH |
| Final | 5/18/2023 | OK to Issue CofO | JON MCHUGH |
| HVAC-Final | 5/18/2023 | Approved | JON MCHUGH |
| PLUMBING-Final | 5/18/2023 | Approved | JON MCHUGH |