17630-17632 W LEMARSH ST 91325

Certificate Information: 17630-17632 W LEMARSH ST 91325

Application / Permit
22016-20000-30146
Plan Check / Job No.
B22VN14847
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: CONVERT PORTION OF (E) 1-STORY SINGLE FAMILY DWELLING AND ATTACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 12/10/2022
Issuing Office
Current Status
CofO Issued on 7/22/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2022 APPLICANT
Assigned to Plan Check Engineer 10/7/2022 DANIEL YIP
Corrections Issued 10/11/2022 DANIEL YIP
Plan Check Approved 10/20/2022 DANIEL YIP
Issued 12/10/2022 APPLICANT
CofO in Progress 7/3/2025 CHRISTOPHER ROJAS
CofO in Progress 7/7/2025 CHRISTOPHER ROJAS
Permit Finaled 7/22/2025 RUBEN SALAS
CofO Issued 7/22/2025 RUBEN SALAS
Permit Finaled 7/22/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 10/17/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 10/17/2022 COLIN LOREDO
Sewer availability Cleared 10/17/2022 COLIN LOREDO

Contact Information

Contractor Rnr Builders Inc; Lic. No.: 804188-B       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/31/2023 Not Ready for Inspection JOHN COLEMAN
Pre-Inspection 1/31/2023 Corrections Issued JOHN COLEMAN
Underground Mechanical 1/31/2023 Approved JOHN COLEMAN
Excavation/Setback/Form/Re-Bar 2/7/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 2/7/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 3/3/2023 Corrections Issued JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 3/3/2023 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 3/14/2023 Not Ready for Inspection JAVIER RAMOS JR
Insulation 3/14/2023 Approved JAVIER RAMOS JR
Rough-Elec/Plmb/HVAC 3/14/2023 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/12/2023 Approved JAVIER RAMOS JR
Drywall Nailing 4/12/2023 Approved JAVIER RAMOS JR
Verify Sprinkler Sign Off 4/12/2023 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 4/25/2023 Approved JAVIER RAMOS JR
Shower Pan 4/25/2023 Approved JAVIER RAMOS JR
ELECTRICAL-Final 6/1/2023 Approved JAVIER RAMOS JR
Final 6/1/2023 Corrections Issued JAVIER RAMOS JR
HVAC-Final 6/1/2023 Approved JAVIER RAMOS JR
PLUMBING-Final 6/1/2023 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 6/1/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 6/1/2023 Approved JAVIER RAMOS JR
Final 7/3/2025 OK to Issue CofO CHRISTOPHER ROJAS