8167-8169 N MATILIJA AVE 91402
Certificate Information: 8167-8169 N MATILIJA AVE 91402
- Application / Permit
- 22016-20000-30021
- Plan Check / Job No.
- B22VN14790
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* CONVERT PORTION (376 SF) OF (E) 1-STORY SFD TO ADU PER CA GC 65852.2(e)(1)(A). ALL CONSTRUCTION PER WFPP. No structural work. No new openings. No change to RFA.
- Permit Issued
- Issued on 11/30/2022
- Issuing Office
- Current Status
- CofO Issued on 9/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2022 | VIVIAN LAO |
| Corrections Issued | 10/13/2022 | VIVIAN LAO |
| Plan Check Approved | 11/30/2022 | VIVIAN LAO |
| Issued | 11/30/2022 | APPLICANT |
| CofO in Progress | 7/27/2023 | GREGG CUMMINGS |
| Permit Finaled | 9/6/2023 | RUBEN SALAS |
| CofO Issued | 9/6/2023 | RUBEN SALAS |
| Permit Finaled | 9/6/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/19/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 10/19/2022 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 3/7/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 3/7/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 3/7/2023 | Approved | GREGG CUMMINGS |
| Sewer | 3/7/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/23/2023 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/23/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 3/23/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 3/23/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 3/23/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 4/6/2023 | Approved | GREGG CUMMINGS |
| Green Building Rough | 4/6/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 4/6/2023 | Approved | GREGG CUMMINGS |
| Insulation | 4/6/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 4/20/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 4/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 4/20/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 5/1/2023 | Partial Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/5/2023 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 5/5/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/17/2023 | Approved | MISAEL ESPARZA |
| Final | 7/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 7/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 7/17/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 7/17/2023 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 7/17/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 7/17/2023 | Not Required | MISAEL ESPARZA |
| Smoke Detectors | 7/17/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 7/26/2023 | OK to Issue CofO | GREGG CUMMINGS |
| Green Building Final | 7/26/2023 | Approved | GREGG CUMMINGS |
| HVAC-Final | 7/26/2023 | Approved | GREGG CUMMINGS |
| Service/Power Release | 7/26/2023 | Approved | GREGG CUMMINGS |
| Smoke Detectors | 7/26/2023 | Approved | GREGG CUMMINGS |