16001-16001 1/2 W CALAHAN ST 91343
Certificate Information: 16001-16001 1/2 W CALAHAN ST 91343
- Application / Permit
- 22016-20000-29958
- Plan Check / Job No.
- B22VN14768
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan Convert existing attached garage (22'-1" x 19'-11 = 440 SF ) to Accessory Dwelling Unit (ADU) ADU CHECKED PER GCS 65852.2(E)(1)(A)
- Permit Issued
- Issued on 3/3/2023
- Issuing Office
- Current Status
- CofO Issued on 11/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/20/2022 | DANIEL YIP |
| Corrections Issued | 10/21/2022 | SUNMIN LEE |
| Applicant returned to address corrections | 2/27/2023 | DANIEL YIP |
| Plan Check Approved | 3/1/2023 | DANIEL YIP |
| Issued | 3/3/2023 | APPLICANT |
| CofO in Progress | 10/19/2023 | RAUL OLAGI |
| Permit Finaled | 11/28/2023 | RUBEN SALAS |
| CofO Issued | 11/28/2023 | RUBEN SALAS |
| Permit Finaled | 11/28/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 10/27/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/27/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2022 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 11/3/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Homescapes Design And Construction Inc; Lic. No.: 1055222-B | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/9/2023 | Conditional Approval | MICHAEL SMITH |
| Footing/Foundation/Slab | 5/10/2023 | Corrections Issued | WILLIAM WREN |
| Footing/Foundation/Slab | 5/12/2023 | Approved | RAUL OLAGI |
| PLUMBING-Rough | 5/12/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/2/2023 | Corrections Issued | RAUL OLAGI |
| BUILDING-Rough-Frame | 6/13/2023 | Corrections Issued | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Corrections Issued | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 6/14/2023 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 6/20/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Rough | 6/20/2023 | Approved | RAUL OLAGI |
| HVAC-Rough | 6/20/2023 | Partial Approval | RAUL OLAGI |
| PLUMBING-Rough | 6/20/2023 | Approved | RAUL OLAGI |
| Insulation | 6/28/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 6/28/2023 | Partial Approval | RAUL OLAGI |
| Shower Pan | 6/28/2023 | Approved | RAUL OLAGI |
| Drywall Nailing | 7/10/2023 | Approved | RAUL OLAGI |
| Interior/Exterior Lathing | 7/10/2023 | Approved | RAUL OLAGI |
| ELECTRICAL-Final | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| Final | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 8/25/2023 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 8/25/2023 | SGSOV Approved | RAUL OLAGI |
| ELECTRICAL-Final | 10/2/2023 | Approved | RAUL OLAGI |
| Final | 10/2/2023 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 10/2/2023 | Approved | RAUL OLAGI |
| PLUMBING-Final | 10/2/2023 | Approved | RAUL OLAGI |
| Smoke Detectors | 10/2/2023 | Approved | RAUL OLAGI |
| Final | 10/19/2023 | OK to Issue CofO | RAUL OLAGI |