17123 W ALBERS ST 91316
Certificate Information: 17123 W ALBERS ST 91316
- Application / Permit
- 22016-20000-29867
- Plan Check / Job No.
- B22VN14720
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) IRREGULAR SHAPE 12'-6"X14'-8" ADDITION AND INTERIOR REMODEL . NFPA-13D FIRE SPRINKLERS REQUIRED THRU-OUT
- Permit Issued
- Issued on 9/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/3/2022 | JESSE ARELLANO |
| Corrections Issued | 10/4/2022 | JESSE ARELLANO |
| Applicant returned to address corrections | 10/12/2022 | JESSE ARELLANO |
| Building Plans Picked Up | 10/17/2022 | APPLICANT |
| Applicant returned to address corrections | 6/21/2023 | JESSE ARELLANO |
| Applicant returned to address corrections | 7/18/2023 | JESSE ARELLANO |
| Plan Check Approved | 8/3/2023 | JESSE ARELLANO |
| Issued | 9/20/2023 | APPLICANT |
| CofO in Progress | 10/20/2024 | JON MCHUGH |
| Permit Finaled | 11/12/2024 | JOHN JANSON |
| CofO Issued | 11/12/2024 | JOHN JANSON |
| Permit Finaled | 11/12/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/24/2023 | COLIN LOREDO |
| Roof/Waste drainage to street | Cleared | 7/24/2023 | COLIN LOREDO |
| Sewer availability | Cleared | 7/24/2023 | COLIN LOREDO |
Contact Information
| Architect | Honles,, Guillermo; Lic. No.: C24928 | 9825 SHADOW ISLAND DRIVE SHADOW HILLS, CA 91040 |
| Contractor | Manchen Construction Inc; Lic. No.: 1043435-B | 18321 VENTURA BLVD #900 TARZANA, CA 91356 |
| Engineer | Niver,, Ron; Lic. No.: C84825 | 10845 LINDBROOK DR 203 LOS ANGELES, CA 90024 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/20/2023 | Approved | JON MCHUGH |
| Sewer | 11/30/2023 | Partial Inspection | MORRIS JACKSON |
| PLUMBING-Rough | 12/27/2023 | Partial Approval | JEFFREY PARD |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Rough | 1/16/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 2/2/2024 | Corrections Issued | JON MCHUGH |
| Sewer | 2/2/2024 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 2/6/2024 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 2/16/2024 | Partial Approval | JON MCHUGH |
| Deputy Drilled-In Anchors | 2/16/2024 | Corrections Issued | JON MCHUGH |
| Interior/Exterior Lathing | 2/16/2024 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 3/4/2024 | Not Ready for Inspection | JON MCHUGH |
| ELECTRICAL-Rough | 3/4/2024 | Approved | JON MCHUGH |
| Green Building Rough | 3/4/2024 | Not Ready for Inspection | JON MCHUGH |
| HVAC-Rough | 3/4/2024 | Corrections Issued | JON MCHUGH |
| MERV13>=Rough | 3/4/2024 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 3/4/2024 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 3/8/2024 | Approved | JEFFREY PARD |
| Green Building Rough | 3/8/2024 | Approved | JEFFREY PARD |
| HVAC-Rough | 3/8/2024 | Approved | JEFFREY PARD |
| Interior/Exterior Lathing | 3/8/2024 | Approved | JEFFREY PARD |
| Insulation | 3/14/2024 | Approved | JON MCHUGH |
| Drywall Nailing | 3/19/2024 | Partial Approval | HENRY KIM |
| Shower Pan | 3/19/2024 | Partial Approval | HENRY KIM |
| Drywall Nailing | 3/26/2024 | Not Ready for Inspection | HORACE FULTZ |
| Interior/Exterior Lathing | 3/26/2024 | Partial Approval | HORACE FULTZ |
| Shower Pan | 3/26/2024 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 9/13/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 9/13/2024 | Corrections Issued | JON MCHUGH |
| ELECTRICAL-Final | 9/25/2024 | Approved | JON MCHUGH |
| HVAC-Final | 9/25/2024 | Corrections Issued | JON MCHUGH |
| PLUMBING-Final | 9/25/2024 | Approved | JON MCHUGH |
| Smoke Detectors | 9/25/2024 | Approved | JON MCHUGH |
| Final | 10/18/2024 | OK to Issue CofO | JON MCHUGH |
| Green Building Final | 10/18/2024 | Approved | JON MCHUGH |
| HVAC-Final | 10/18/2024 | Approved | JON MCHUGH |
| MERV13>=Final | 10/18/2024 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/18/2024 | SGSOV Approved | JON MCHUGH |