3620 S MCCLINTOCK AVE 90089

Certificate Information: 3620 S MCCLINTOCK AVE 90089

Application / Permit
22016-20000-29841
Plan Check / Job No.
B22VN14686
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) College
Work Description
EPLAN REMODEL (E) UNDERGROUND FIRE PUMP VAULT AND REMODEL STEEL TRELLIS ENCLOSURE
Permit Issued
Issued on 6/21/2023
Issuing Office
Current Status
Issued on 6/21/2023

Permit Application Status History

Submitted 9/30/2022 APPLICANT
Assigned to Plan Check Engineer 10/6/2022 RAPHAEL ROSAS
Corrections Issued 10/11/2022 RAPHAEL ROSAS
Quality Review Completed 10/21/2022 STEVEN KIM
Applicant returned to address corrections 3/13/2023 RAPHAEL ROSAS
Plan Check Approved 6/15/2023 RAPHAEL ROSAS
Issued 6/21/2023 APPLICANT

Permit Application Clearance Information

Historic monument Cleared 10/26/2022 MAX LODER
Specific Plan Cleared 10/26/2022 RAFAEL FONTES
ZA Case Cleared 10/26/2022 MAXFIELD VERMY
ZI Cleared 10/26/2022 MAXFIELD VERMY
ZI Cleared 10/26/2022 RAFAEL FONTES
ZI Cleared 10/26/2022 RAFAEL FONTES
Green Code Cleared 11/3/2022 MICHAEL AYERS
Metro Rail approval Cleared 11/18/2022 RAPHAEL ROSAS
Fire Marshal Fire Life Safety Cleared 5/17/2023 ANDREW KO
DAS Clearance Cleared 5/30/2023 RAPHAEL ROSAS

Contact Information

Contractor Pinnacle Contracting Corporation; Lic. No.: 665647-B 21800 BURBANK BLVD #210      WOODLAND HILLS, CA 91367
Engineer Caravalho,, Kim; Lic. No.: S4896 541 LINWOOD AVENUE UNIT A      MONROVIA, CA 91016
Engineer Tang,, Stanley Siu Kei; Lic. No.: C56178 1105 N AVON STREET      BURBANK, CA 91505

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/21/2023 Corrections Issued ALAN MORELOS
Excavation/Setback/Form/Re-Bar 7/24/2023 Partial Approval ALAN MORELOS
Footing/Foundation/Slab 7/24/2023 Partial Approval ALAN MORELOS
Excavation/Setback/Form/Re-Bar 8/3/2023 Partial Approval ALAN MORELOS
Footing/Foundation/Slab 9/15/2023 Not Ready for Inspection ALAN MORELOS
Light Gage Steel Frame 11/16/2023 Partial Approval LUIS CCAMACHO
Interior/Exterior Lathing 11/30/2023 Partial Approval LUIS CCAMACHO
Drywall Nailing 12/14/2023 Partial Approval LUIS CCAMACHO
Pre-Inspection 1/30/2024 Partial Approval LUIS CCAMACHO
T-Bar Ceiling 2/16/2024 Partial Approval MARTIN TAVITIAN
Final 9/19/2024 Conditional Approval ALFREDO LOPEZ
Green Building Final 9/19/2024 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 9/19/2024 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 9/19/2024 Approved ALFREDO LOPEZ