19012 W INGOMAR ST 91335

Certificate Information: 19012 W INGOMAR ST 91335

Application / Permit
22016-20000-29776
Plan Check / Job No.
B22VN14655
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convert (E) Garage to ADU PER STATE LAW ALL WORK DONE PER WFPP
Permit Issued
Issued on 5/8/2023
Issuing Office
Current Status
CofO Issued on 4/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2022 APPLICANT
Assigned to Plan Check Engineer 10/12/2022 HERNAN ARREOLA
Corrections Issued 10/12/2022 HERNAN ARREOLA
Applicant returned to address corrections 2/3/2023 KHUONG TRUONG
Plan Check Approved 2/22/2023 KHUONG TRUONG
Issued 5/8/2023 APPLICANT
CofO in Progress 12/26/2024 ARUTYUN MADATYAN
No Progress 1/14/2025 SEAN WIRCH
CofO in Progress 1/14/2025 SEAN WIRCH
Permit Finaled 4/3/2025 JOHN JANSON
CofO Issued 4/3/2025 JOHN JANSON
Permit Finaled 4/3/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/26/2022 CARLOS AGUILERA
Sewer availability Cleared 10/26/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/9/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/20/2023 Conditional Approval HENRY KIM
Footing/Foundation/Slab 6/21/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 6/30/2023 Approved JEFFREY BULL
ELECTRICAL-Rough 6/30/2023 Approved JEFFREY BULL
Green Building Rough 6/30/2023 Not Ready for Inspection JEFFREY BULL
HVAC-Rough 6/30/2023 Approved JEFFREY BULL
PLUMBING-Rough 6/30/2023 Approved JEFFREY BULL
Insulation 7/3/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 7/3/2023 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 7/6/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 7/6/2023 Approved JEFFREY BULL
Drywall Nailing 7/7/2023 Approved JEFFREY BULL
Underground Mechanical 8/11/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 11/15/2024 Approved ARUTYUN MADATYAN
Final 11/15/2024 Corrections Issued ARUTYUN MADATYAN
Green Building Final 11/15/2024 Approved ARUTYUN MADATYAN
Green Building Rough 11/15/2024 Approved ARUTYUN MADATYAN
SGSOV-Seismic Gas S/O Valve 11/15/2024 SGSOV Approved ARUTYUN MADATYAN
Service/Power Release 11/15/2024 Approved ARUTYUN MADATYAN
Smoke Detectors 11/15/2024 Approved ARUTYUN MADATYAN
ELECTRICAL-Final 12/24/2024 Approved ARUTYUN MADATYAN
Final 12/24/2024 OK to Issue CofO ARUTYUN MADATYAN
HVAC-Final 12/24/2024 Approved ARUTYUN MADATYAN
PLUMBING-Final 12/24/2024 Approved ARUTYUN MADATYAN