19012 W INGOMAR ST 91335
Certificate Information: 19012 W INGOMAR ST 91335
- Application / Permit
- 22016-20000-29776
- Plan Check / Job No.
- B22VN14655
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert (E) Garage to ADU PER STATE LAW ALL WORK DONE PER WFPP
- Permit Issued
- Issued on 5/8/2023
- Issuing Office
- Current Status
- CofO Issued on 4/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2022 | HERNAN ARREOLA |
| Corrections Issued | 10/12/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 2/3/2023 | KHUONG TRUONG |
| Plan Check Approved | 2/22/2023 | KHUONG TRUONG |
| Issued | 5/8/2023 | APPLICANT |
| CofO in Progress | 12/26/2024 | ARUTYUN MADATYAN |
| No Progress | 1/14/2025 | SEAN WIRCH |
| CofO in Progress | 1/14/2025 | SEAN WIRCH |
| Permit Finaled | 4/3/2025 | JOHN JANSON |
| CofO Issued | 4/3/2025 | JOHN JANSON |
| Permit Finaled | 4/3/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/26/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/20/2023 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 6/21/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 6/30/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 6/30/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 6/30/2023 | Not Ready for Inspection | JEFFREY BULL |
| HVAC-Rough | 6/30/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 6/30/2023 | Approved | JEFFREY BULL |
| Insulation | 7/3/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 7/3/2023 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 7/6/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 7/7/2023 | Approved | JEFFREY BULL |
| Underground Mechanical | 8/11/2023 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 11/15/2024 | Approved | ARUTYUN MADATYAN |
| Final | 11/15/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 11/15/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 11/15/2024 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | ARUTYUN MADATYAN |
| Service/Power Release | 11/15/2024 | Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 11/15/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 12/24/2024 | Approved | ARUTYUN MADATYAN |
| Final | 12/24/2024 | OK to Issue CofO | ARUTYUN MADATYAN |
| HVAC-Final | 12/24/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 12/24/2024 | Approved | ARUTYUN MADATYAN |