17333 W GILMORE ST 91406
Certificate Information: 17333 W GILMORE ST 91406
- Application / Permit
- 22016-20000-29759
- Plan Check / Job No.
- B22VN14648
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. CONVERT EXISTING 1-STORY DETACHED GARAGE TO ACCESSORY DWELLING UNIT WITH 1-STORY ADDITION.
- Permit Issued
- Issued on 1/27/2023
- Issuing Office
- Current Status
- CofO Issued on 10/30/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2022 | PRANITA SHAH |
| Corrections Issued | 10/10/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 12/23/2022 | PRANITA SHAH |
| Applicant returned to address corrections | 1/23/2023 | DAVID CASTILLO |
| Plan Check Approved | 1/27/2023 | DAVID CASTILLO |
| Issued | 1/27/2023 | APPLICANT |
| CofO in Progress | 10/6/2023 | SEAN HAUPT |
| Permit Finaled | 10/30/2023 | JOHN JANSON |
| CofO Issued | 10/30/2023 | JOHN JANSON |
| Permit Finaled | 10/30/2023 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 10/13/2022 | COLIN LOREDO |
| ZI | Cleared | 10/19/2022 | NELSON RODRIGUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2022 | COLIN LOREDO |
| Sewer availability | Cleared | 12/20/2022 | COLIN LOREDO |
| Construction near power lines | Cleared | 12/22/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 1/19/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 1/19/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/7/2023 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 2/14/2023 | Approved | JON MCHUGH |
| Wood Frame | 3/7/2023 | Not Ready for Inspection | JON MCHUGH |
| BUILDING-Rough-Frame | 3/8/2023 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Partial Approval | JON MCHUGH |
| Green Building Rough | 3/8/2023 | Not Ready for Inspection | JON MCHUGH |
| Wood Frame | 3/8/2023 | Not Ready for Inspection | JON MCHUGH |
| PLUMBING-Rough | 3/17/2023 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Corrections Issued | JON MCHUGH |
| Rough-Elec/Plmb/HVAC | 4/3/2023 | Corrections Issued | JON MCHUGH |
| Deputy Wood Construction | 4/6/2023 | Conditional Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 4/11/2023 | Approved | SEAN HAUPT |
| Green Building Rough | 4/11/2023 | Not Ready for Inspection | SEAN HAUPT |
| Rough-Elec/Plmb/HVAC | 4/11/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/17/2023 | Partial Approval | JOHN KIDWELL |
| Insulation | 4/19/2023 | Approved | SEAN HAUPT |
| Pre-Inspection | 4/19/2023 | Partial Inspection | JUSTIN HAWLEY |
| Shower Pan | 4/19/2023 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/21/2023 | Corrections Issued | JON MCHUGH |
| Drywall Nailing | 4/26/2023 | Approved | SEAN HAUPT |
| Shower Pan | 4/26/2023 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 7/28/2023 | Corrections Issued | JEFFREY BULL |
| ELECTRICAL-Final | 8/29/2023 | Approved | JUSTIN HAWLEY |
| BUILDING-Rough-Frame | 9/27/2023 | Corrections Issued | JON MCHUGH |
| Final | 9/27/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 9/27/2023 | Not Ready for Inspection | JON MCHUGH |
| Green Building Rough | 9/27/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Not Ready | JON MCHUGH |
| Smoke Detectors | 9/27/2023 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 10/3/2023 | Approved | JON MCHUGH |
| Final | 10/3/2023 | Corrections Issued | JON MCHUGH |
| Green Building Final | 10/3/2023 | Approved | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 10/3/2023 | SGSOV Approved | JON MCHUGH |
| ELECTRICAL-Final | 10/5/2023 | Approved | SEAN HAUPT |
| Final | 10/5/2023 | OK to Issue CofO | SEAN HAUPT |
| Green Building Final | 10/5/2023 | Approved | SEAN HAUPT |
| HVAC-Final | 10/5/2023 | Approved | SEAN HAUPT |
| PLUMBING-Final | 10/5/2023 | Approved | SEAN HAUPT |
| PLUMBING-Rough | 10/5/2023 | Not Ready for Inspection | SEAN HAUPT |
| Sewer | 10/5/2023 | Not Ready for Inspection | SEAN HAUPT |