6102 N WILLOW CREST AVE 91606

Certificate Information: 6102 N WILLOW CREST AVE 91606

Application / Permit
22016-20000-29325
Plan Check / Job No.
B22VN14463
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTNG GARAGE 369.5 S.F. INTO AN A.D.U.
Permit Issued
Issued on 7/21/2023
Issuing Office
Current Status
Issued on 7/21/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/11/2022 APPLICANT
Assigned to Plan Check Engineer 12/16/2022 JOE VO
Corrections Issued 12/19/2022 JOE VO
Plan Check Approved 7/14/2023 JOE VO
Issued 7/21/2023 APPLICANT

Permit Application Clearance Information

Address approval Cleared 1/10/2023 COLIN LOREDO
Sewer availability Cleared 1/10/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 1/13/2023 COLIN LOREDO
Construction within easement Cleared 7/11/2023 WALTER RAMIREZ

Contact Information

Contractor Holloway Design And Construction Inc; Lic. No.: 1071632-B       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/24/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/4/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/9/2023 No Access for Inspection JOHN HAYES
Footing/Foundation/Slab 8/9/2023 No Access for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/15/2023 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 8/15/2023 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 8/21/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 8/21/2023 Corrections Issued JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 8/24/2023 Partial Approval JOHN HAYES
Footing/Foundation/Slab 8/24/2023 Partial Approval JOHN HAYES
Underground Mechanical 8/24/2023 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 11/9/2023 Corrections Issued JOHN HAYES
Rough-Elec/Plmb/HVAC 11/9/2023 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 12/5/2023 No Access for Inspection JOHN COLEMAN
ELECTRICAL-Rough 12/14/2023 No Access for Inspection JOHN HAYES
HVAC-Rough 12/14/2023 No Access for Inspection JOHN HAYES
PLUMBING-Rough 12/14/2023 No Access for Inspection JOHN HAYES
ELECTRICAL-Rough 1/12/2024 Corrections Issued CHRISTOPHER ROJAS
HVAC-Rough 1/12/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 1/12/2024 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 1/19/2024 Corrections Issued JOHN COLEMAN
Rough-Elec/Plmb/HVAC 1/19/2024 Corrections Issued JOHN COLEMAN
Rough-Elec/Plmb/HVAC 1/24/2024 Corrections Issued JOHN COLEMAN
ELECTRICAL-Rough 6/21/2024 Partial Approval JOSE AVILA
HVAC-Rough 6/21/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 6/21/2024 Approved JOSE AVILA
Sewer 6/21/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 8/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 8/5/2024 Approved ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 8/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Structural Steel Frame 8/5/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Wood Frame 8/5/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 8/15/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 9/20/2024 Approved JOSE AVILA
ELECTRICAL-Rough 9/20/2024 Approved JOSE AVILA
HVAC-Rough 9/20/2024 Conditional Approval JOSE AVILA
Insulation 10/1/2024 Corrections Issued JOSE AVILA
Interior/Exterior Lathing 10/1/2024 Partial Approval JOSE AVILA
Drywall Nailing 10/31/2024 Approved JOSE AVILA
Shower Pan 11/25/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 12/9/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 12/18/2025 No Access for Inspection JOSE AVILA
ELECTRICAL-Final 1/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 1/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 1/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 1/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 1/16/2026 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Smoke Detectors 1/16/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 1/29/2026 Approved JAVIER RAMOS JR
Final 1/29/2026 Partial Approval JAVIER RAMOS JR
HVAC-Final 1/29/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 1/29/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/29/2026 SGSOV Approved JAVIER RAMOS JR
Service/Power Release 1/29/2026 Approved JAVIER RAMOS JR
Smoke Detectors 1/29/2026 Approved JAVIER RAMOS JR