15430 W ROSCOE BLVD 91406
Certificate Information: 15430 W ROSCOE BLVD 91406
- Application / Permit
- 22016-20000-29308
- Plan Check / Job No.
- B22VN14454
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Auto Repair Garage
- Work Description
- Fire Damage Repair of (e) automotive dealership building and interior tenant improvement of existing service shop and parts storage.
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Current Status
- Permit Finaled on 9/26/2024
Permit Application Status History
| Submitted | 9/26/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/29/2022 | JOE VO |
| Corrections Issued | 10/1/2022 | JOE VO |
| Quality Review Completed | 10/3/2022 | GARO TELMI |
| Plan Check Approved | 11/4/2022 | JOE VO |
| No Progress | 11/7/2022 | JOE VO |
| Plan Check Approved | 11/7/2022 | JOE VO |
| Issued | 11/10/2022 | APPLICANT |
| Permit Finaled | 9/11/2024 | DANNY RODRIGUEZ |
Permit Application Clearance Information
| "Q" conditions | Cleared | 10/24/2022 | KENTON TRINH |
| "T" removal | Cleared | 10/24/2022 | KENTON TRINH |
| CPC | Cleared | 10/24/2022 | KENTON TRINH |
| Green Code | Cleared | 10/26/2022 | MICHAEL AYERS |
| DAS Clearance | Cleared | 10/28/2022 | Joe Vo |
Contact Information
| Architect | , ; Lic. No.: NA37423 | , |
| Contractor | Kunzik & Sara Construction Inc; Lic. No.: 847939-B | 1699 LA COSTA MEADOWS DR #102 SAN MARCOS, CA 92078 |
| Engineer | Chen,, Jeff Y; Lic. No.: S4699 | 17500 REDHILL AVENUE SUITE 240 IRVINE, CA 92614 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/17/2023 | Conditional Approval | CAMERON CHABAN |
| Wood Frame | 4/18/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Deputy Wood Construction | 4/20/2023 | Conditional Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 4/24/2023 | Conditional Approval | ANDREW DORSO |
| Deputy Wood Construction | 5/15/2023 | Conditional Approval | ANDREW DORSO |
| Deputy Wood Construction | 5/16/2023 | Conditional Approval | DANNY RODRIGUEZ |
| Footing/Foundation/Slab | 5/16/2023 | Partial Approval | CAMERON CHABAN |
| Wood Frame | 5/19/2023 | Corrections Issued | ANDREW DORSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Approved | ANDREW DORSO |
| Deputy Drilled-In Anchors | 5/30/2023 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 5/30/2023 | Conditional Approval | ANDREW DORSO |
| Deputy Drilled-In Anchors | 6/2/2023 | Conditional Approval | ANDREW DORSO |
| Footing/Foundation/Slab | 6/13/2023 | Corrections Issued | ANDREW DORSO |
| Light Gage Steel Frame | 6/30/2023 | Approved | ANDREW DORSO |
| Deputy Drilled-In Anchors | 7/10/2023 | Conditional Approval | ANDREW DORSO |
| Drywall Nailing | 7/10/2023 | Approved | KENNETH ROBERTS |
| Interior/Exterior Lathing | 7/24/2023 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 3/11/2024 | Partial Inspection | ANDREW DORSO |
| T-Bar Ceiling | 3/19/2024 | Approved | ANDREW DORSO |
| Pre-Inspection | 5/16/2024 | Partial Inspection | ANDREW DORSO |
| Final | 9/11/2024 | Permit Finaled | DANNY RODRIGUEZ |
| Green Building Final | 9/11/2024 | Approved | DANNY RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/11/2024 | SGSOV No Gas | DANNY RODRIGUEZ |
| Smoke Detectors | 9/11/2024 | Approved | DANNY RODRIGUEZ |