6251 N TAMPA AVE 91335

Certificate Information: 6251 N TAMPA AVE 91335

Application / Permit
22016-20000-29036
Plan Check / Job No.
B22VN14355
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* CONVERT (E) DETACHED 2-CAR GARAGE TO ADU PER GC 65852.2(e)(1)(A).
Permit Issued
Issued on 11/28/2022
Issuing Office
Current Status
CofO Issued on 6/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/23/2022 APPLICANT
Assigned to Plan Check Engineer 9/28/2022 VIVIAN LAO
Corrections Issued 9/29/2022 VIVIAN LAO
Plan Check Approved 10/26/2022 VIVIAN LAO
Issued 11/28/2022 APPLICANT
CofO in Progress 5/26/2023 ALEXANDER HANDY
Permit Finaled 6/13/2023 JOHN JANSON
CofO Issued 6/13/2023 JOHN JANSON
Permit Finaled 6/13/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 10/11/2022 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 10/11/2022 LEE GUILBEAUX
Sewer availability Cleared 10/11/2022 LEE GUILBEAUX
ZI Cleared 10/12/2022 DANIEL CORONADO
Eng Process Fee Ord 176,300 Cleared 10/13/2022 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/30/2023 Approved ALEXANDER HANDY
Excavation/Setback/Form/Re-Bar 2/17/2023 Not Ready for Inspection ALEXANDER HANDY
PLUMBING-Rough 2/17/2023 Partial Approval ALEXANDER HANDY
Deputy Drilled-In Anchors 2/21/2023 Conditional Approval ALEXANDER HANDY
Footing/Foundation/Slab 2/23/2023 Approved JESUS PINEDA
Sewer 3/7/2023 Corrections Issued DAVID SANDOVAL
Sewer 3/8/2023 Approved ALEXANDER HANDY
Underground Mechanical 3/8/2023 Approved ALEXANDER HANDY
ELECTRICAL-Rough 3/28/2023 Approved HORACE FULTZ
Floor/Roof Diaphrgm/Shear Wall 3/28/2023 Not Ready for Inspection HORACE FULTZ
PLUMBING-Rough 3/28/2023 Corrections Issued HORACE FULTZ
Wood Frame 3/28/2023 Not Ready for Inspection HORACE FULTZ
ELECTRICAL-Rough 3/31/2023 Partial Inspection KRISTEN CAUSEY
Floor/Roof Diaphrgm/Shear Wall 4/3/2023 Approved JON MCHUGH
Rough-Elec/Plmb/HVAC 4/3/2023 Corrections Issued JON MCHUGH
Insulation 4/4/2023 Not Ready for Inspection KRISTEN CAUSEY
ELECTRICAL-Rough 4/7/2023 Approved ALEXANDER HANDY
HVAC-Rough 4/7/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 4/7/2023 Partial Approval ALEXANDER HANDY
PLUMBING-Rough 4/7/2023 Approved ALEXANDER HANDY
Insulation 4/10/2023 Not Ready for Inspection KRISTEN CAUSEY
BUILDING-Rough-Frame 4/12/2023 Approved ALEXANDER HANDY
Drywall Nailing 4/12/2023 Approved ALEXANDER HANDY
Green Building Rough 4/12/2023 Approved ALEXANDER HANDY
Insulation 4/12/2023 Approved ALEXANDER HANDY
Wood Frame 4/12/2023 Approved ALEXANDER HANDY
Final 5/23/2023 Corrections Issued ALEXANDER HANDY
Green Building Final 5/23/2023 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 5/23/2023 SGSOV Not Required ALEXANDER HANDY
Smoke Detectors 5/23/2023 Approved ALEXANDER HANDY
Final 5/26/2023 OK to Issue CofO ALEXANDER HANDY
Green Building Final 5/26/2023 Approved ALEXANDER HANDY