1245-1247 W 22ND ST 90007
Certificate Information: 1245-1247 W 22ND ST 90007
- Application / Permit
- 22016-20000-28964
- Plan Check / Job No.
- B22VN14322
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- COMPLETE INT REMODEL OF 2ND FLR UNIT (1245 W 22ND ST). AT 1ST FLR UNIT (1247 W 22ND ST) BELOW, PROVIDE NEW COLUMNS PER PLAN DUE TO REMODEL ABOVE.
- Permit Issued
- Issued on 1/19/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 12/18/2025
Permit Application Status History
| Submitted | 9/22/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2022 | LUIS RINCON |
| Corrections Issued | 9/24/2022 | LUIS RINCON |
| Building Plans Picked Up | 9/27/2022 | APPLICANT |
| Applicant returned to address corrections | 11/7/2022 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 11/23/2022 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/12/2023 | ANGELICA MARTINEZ |
| Issued | 1/19/2023 | APPLICANT |
| Permit Finaled | 5/20/2025 | ALFREDO LOPEZ |
Permit Application Clearance Information
| ZA Case | Cleared | 10/12/2022 | DALIA MOKAYED |
| ZA Case | Cleared | 10/12/2022 | DALIA MOKAYED |
| Address approval | Cleared | 10/15/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2022 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 11/14/2022 | MICHAEL SOTO |
| HPOZ | Cleared | 12/29/2022 | MICAELA TORRES-GIL |
| ZI | Cleared | 12/29/2022 | MICAELA TORRES-GIL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/29/2023 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 6/29/2023 | Partial Approval | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 7/5/2023 | Approved | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 7/5/2023 | Approved | MARTIN TAVITIAN |
| Final | 8/8/2023 | Corrections Issued | ALAN MORELOS |
| SGSOV-Seismic Gas S/O Valve | 8/8/2023 | SGSOV Not Ready | ALAN MORELOS |
| Smoke Detectors | 8/8/2023 | Not Ready for Inspection | ALAN MORELOS |
| Final | 12/15/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 12/15/2023 | SGSOV Not Ready | MARTIN TAVITIAN |
| Smoke Detectors | 12/15/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Insulation | 4/16/2024 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 4/18/2024 | Approved | ALFREDO LOPEZ |
| Drywall Nailing | 5/7/2024 | Approved | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 8/15/2024 | Approved | ALFREDO LOPEZ |
| Final | 5/20/2025 | Permit Finaled | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/20/2025 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 5/20/2025 | Approved | ALFREDO LOPEZ |