7547-7549 W APPERSON ST 91042
Certificate Information: 7547-7549 W APPERSON ST 91042
- Application / Permit
- 22016-20000-28816
- Plan Check / Job No.
- B22VN14247
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 11'-0" x 20'-0" REMOVAL OF (E)ATTACHED CARPORT AND 13'-0" x 36'-10" IRREGULAR SHAPED TWO STORY ATTACHED ADDITION TO THE (E) SINGLE FAMILY DWELLING FOR A NEW (855S.F) ACCESSORY DWELLING UNIT WITH BALCONY PER LAMC 12.22 A.33(c)and(e)
- Permit Issued
- Issued on 1/26/2023
- Issuing Office
- Current Status
- CofO Issued on 3/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2022 | SARKIS HARABEDIAN |
| Corrections Issued | 9/28/2022 | SARKIS HARABEDIAN |
| Plan Check Approved | 1/20/2023 | SARKIS HARABEDIAN |
| No Progress | 1/26/2023 | SARKIS HARABEDIAN |
| Plan Check Approved | 1/26/2023 | SARKIS HARABEDIAN |
| Issued | 1/26/2023 | APPLICANT |
| CofO in Progress | 2/14/2024 | WILLIAM WREN |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
| CofO Issued | 3/2/2024 | RUBEN SALAS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/29/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 9/29/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2022 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 9/30/2022 | KIRK LINKLATER |
| Sewer availability | Cleared | 9/30/2022 | JOSE DUARTE-DIAZ |
| Public Works-Highway Ded. | Cleared | 9/30/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Karamora Construction Inc; Lic. No.: 1084020-B | , |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/3/2023 | Not Ready for Inspection | WILLIAM WREN |
| Footing/Foundation/Slab | 5/3/2023 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 5/3/2023 | Partial Approval | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 5/10/2023 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 5/10/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 5/30/2023 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2023 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/23/2023 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2023 | Partial Approval | WILLIAM WREN |
| HVAC-Rough | 6/23/2023 | Approved | WILLIAM WREN |
| Shower Pan | 6/23/2023 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 8/3/2023 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 8/3/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 8/3/2023 | Approved | WILLIAM WREN |
| Sewer | 8/3/2023 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2023 | Approved | WILLIAM WREN |
| Insulation | 8/23/2023 | Conditional Approval | WILLIAM WREN |
| Shower Pan | 8/23/2023 | Approved | WILLIAM WREN |
| Insulation | 8/28/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 8/28/2023 | Partial Approval | WILLIAM WREN |
| Drywall Nailing | 9/5/2023 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 9/14/2023 | Approved | WILLIAM WREN |
| Underground Mechanical | 10/26/2023 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Final | 2/13/2024 | Approved | WILLIAM WREN |
| Final | 2/13/2024 | OK to Issue CofO | WILLIAM WREN |
| Green Building Final | 2/13/2024 | Approved | WILLIAM WREN |
| PLUMBING-Final | 2/13/2024 | Approved | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 2/13/2024 | SGSOV Approved | WILLIAM WREN |
| Service/Power Release | 2/13/2024 | Approved | WILLIAM WREN |
| Smoke Detectors | 2/13/2024 | Approved | WILLIAM WREN |