21240 W BURBANK BLVD #31 91367
Certificate Information: 21240 W BURBANK BLVD #31 91367
- Application / Permit
- 22016-20000-28344
- Plan Check / Job No.
- B22VN14048
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- RECONFIGURATION OF EXISTING BUSINESS R+D SPACES TO ACCOMMODATE FOR MORE SUPPORTING WORKSTATIONS AND RESEARCH AREAS. SELECTIVE DEMOLITION OF EXISTING NON-STRUCTURAL PARTITIONS AND CEILING AS NOTED. RECONFIGURATION OF SPACE AS NOTED IN DESIGN. NO CHANGE IN OCCUPANCY OR USE. MECHANICAL, ELECTRICAL, AND PLUMBING UNDER SEPARATE PERMIT OR DESIGN/BUILD.
- Permit Issued
- Issued on 6/27/2023
- Issuing Office
- Current Status
- Permit Finaled on 6/13/2025
Permit Application Status History
| Submitted | 10/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2022 | JOE VO |
| Corrections Issued | 10/18/2022 | JOE VO |
| Plan Check Approved | 11/24/2022 | JOE VO |
| Issued | 6/27/2023 | APPLICANT |
| Permit Finaled | 6/12/2025 | BRIAN KELLY |
Permit Application Clearance Information
| Specific Plan | Cleared | 10/19/2022 | SHEILA AHORAIAN |
| Specific Plan | Cleared | 11/2/2022 | KRISTINE JEGALIAN |
| Hold | Cleared | 9/22/2023 | JEREMY CORONEL |
Contact Information
| Architect | Guerrero,, Mark Anthony; Lic. No.: NA36994 | , |
| Contractor | Hitt Contracting Inc; Lic. No.: 811478-B | , |
Inspector Information
| BRIAN KELLY, (818) 374-1127 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/5/2023 | Partial Approval | BRIAN KELLY |
| Deputy Steel/Welding | 2/15/2024 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 3/11/2024 | Not Ready for Inspection | BRIAN KELLY |
| Light Gage Steel Frame | 3/11/2024 | Partial Approval | BRIAN KELLY |
| Deputy Steel/Welding | 3/12/2024 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 3/13/2024 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 3/14/2024 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 3/15/2024 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 3/20/2024 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 3/20/2024 | Partial Approval | BRIAN KELLY |
| Insulation | 3/20/2024 | Approved | BRIAN KELLY |
| Deputy Steel/Welding | 4/2/2024 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 4/10/2024 | Conditional Approval | BRIAN KELLY |
| Deputy Steel/Welding | 4/11/2024 | Conditional Approval | BRIAN KELLY |
| Drywall Nailing | 5/6/2024 | Partial Approval | BRIAN KELLY |
| Light Gage Steel Frame | 5/6/2024 | Partial Approval | BRIAN KELLY |
| Excavation/Setback/Form/Re-Bar | 5/23/2024 | Partial Approval | BRIAN KELLY |
| Deputy Steel/Welding | 5/29/2024 | Conditional Approval | BRIAN KELLY |
| T-Bar Ceiling | 6/26/2024 | Approved | BRIAN KELLY |
| Final | 6/12/2025 | Permit Finaled | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 6/12/2025 | SGSOV Approved | BRIAN KELLY |
| Smoke Detectors | 6/12/2025 | Approved | BRIAN KELLY |