7341 N NITA AVE 91303

Certificate Information: 7341 N NITA AVE 91303

Application / Permit
22016-20000-28144
Plan Check / Job No.
B22VN14010
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX DETACHED 20'-3"x 20'-3" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITHOUT ADDN. ALL WORK PER ENGR DESIGN.
Permit Issued
Issued on 10/26/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/22/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2022 APPLICANT
Assigned to Plan Check Engineer 9/16/2022 HAYATO TSUCHIYA
Corrections Issued 9/16/2022 HAYATO TSUCHIYA
Building Plans Picked Up 9/19/2022 APPLICANT
Plan Check Approved 10/17/2022 ANGELICA MARTINEZ
Issued 10/26/2022 APPLICANT
CofO in Progress 2/22/2023 CHRIS CHRISTENSEN
Permit Finaled 3/22/2023 JOHN JANSON
CofO Issued 3/22/2023 JOHN JANSON
Permit Finaled 3/22/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/20/2022 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 9/20/2022 COLIN LOREDO
Sewer availability Cleared 9/20/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Gonzalez,, Fernando Francisco; Lic. No.: C53256 11607 AMESTOY AVE      GRANADA HILLS, CA 91344

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/14/2022 Conditional Approval CHRIS CHRISTENSEN
Footing/Foundation/Slab 11/17/2022 Approved CHRIS CHRISTENSEN
Pre-Inspection 11/17/2022 Partial Inspection MORRIS JACKSON
PLUMBING-Rough 12/7/2022 Corrections Issued KRISTEN CAUSEY
Wood Frame 12/7/2022 Corrections Issued KRISTEN CAUSEY
BUILDING-Rough-Frame 12/12/2022 Partial Approval KRISTEN CAUSEY
ELECTRICAL-Rough 12/12/2022 Approved KRISTEN CAUSEY
Green Building Rough 12/12/2022 Not Ready for Inspection KRISTEN CAUSEY
Insulation 12/12/2022 Not Ready for Inspection KRISTEN CAUSEY
PLUMBING-Rough 12/12/2022 Approved KRISTEN CAUSEY
Sewer 12/12/2022 Approved KRISTEN CAUSEY
Gas Test 12/13/2022 Not Ready for Inspection KRISTEN CAUSEY
Insulation 12/14/2022 Approved KRISTEN CAUSEY
Drywall Nailing 12/19/2022 Approved KRISTEN CAUSEY
Green Building Rough 12/19/2022 Approved KRISTEN CAUSEY
Interior/Exterior Lathing 12/19/2022 Partial Approval KRISTEN CAUSEY
Drywall Nailing 12/20/2022 Approved KRISTEN CAUSEY
Gas Test 12/20/2022 Approved KRISTEN CAUSEY
Gas Test 12/23/2022 Approved KRISTEN CAUSEY
Shower Pan 1/4/2023 Approved KRISTEN CAUSEY
BUILDING-Rough-Frame 1/30/2023 Approved CHRIS CHRISTENSEN
Final 1/30/2023 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 1/30/2023 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/30/2023 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 1/30/2023 Approved CHRIS CHRISTENSEN
Final 2/13/2023 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 2/13/2023 Approved CHRIS CHRISTENSEN
Final 2/21/2023 OK to Issue CofO CHRIS CHRISTENSEN