6436 N DENNY AVE 91606
Certificate Information: 6436 N DENNY AVE 91606
- Application / Permit
- 22016-20000-28048
- Plan Check / Job No.
- B22VN13994
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 6/23/2023
- Issuing Office
- Current Status
- CofO Issued on 2/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2022 | DANIEL YIP |
| Corrections Issued | 10/12/2022 | DANIEL YIP |
| Applicant returned to address corrections | 3/28/2023 | DANIEL YIP |
| Applicant returned to address corrections | 5/16/2023 | DANIEL YIP |
| Applicant returned to address corrections | 6/1/2023 | DANIEL YIP |
| Plan Check Approved | 6/17/2023 | DANIEL YIP |
| Issued | 6/23/2023 | APPLICANT |
| CofO in Progress | 2/6/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 2/26/2025 | RUBEN SALAS |
| CofO Issued | 2/26/2025 | RUBEN SALAS |
| Permit Finaled | 2/26/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2022 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 12/6/2022 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2022 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Grandhi,, Venkata Rohit; Lic. No.: C88709 | 7823 BOXWOOD CT HIGHLAND, CA 92346 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/13/2023 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 10/13/2023 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 10/13/2023 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 12/12/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 4/12/2024 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/17/2024 | Not Ready for Inspection | JOSE AVILA |
| Rough-Elec/Plmb/HVAC | 5/17/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 8/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 8/7/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/15/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 8/15/2024 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| Shower Pan | 8/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Rough-Elec/Plmb/HVAC | 8/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Underground Mechanical | 8/30/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 9/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 9/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 9/13/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 12/10/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Gas Test | 12/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/10/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 12/10/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 12/18/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 1/27/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |
| Service/Power Release | 1/27/2025 | Approved | ROBERTO PALACIOS-LOPEZ |