1185-1189 1/2 W 28TH ST 90007

Certificate Information: 1185-1189 1/2 W 28TH ST 90007

Application / Permit
22016-20000-27759
Plan Check / Job No.
B22VN13909
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN: PROPOSED REMODEL AND ADDITION OF ACCESSORY DWELLING UNIT TO APARTMENT BUILDING PER LAMC 12.22 A.33(c) and (e); NFPA-13 FIRE SPRINKLER IS REQUIRED
Permit Issued
Issued on 12/21/2022
Issuing Office
Current Status
CofO Issued on 8/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 SINA KHOSRAVI
Corrections Issued 9/19/2022 SINA KHOSRAVI
Quality Review Completed 9/21/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 10/7/2022 SINA KHOSRAVI
Applicant returned to address corrections 10/25/2022 SINA KHOSRAVI
Applicant returned to address corrections 11/29/2022 SINA KHOSRAVI
Applicant returned to address corrections 12/6/2022 SINA KHOSRAVI
Plan Check Approved 12/21/2022 SINA KHOSRAVI
Issued 12/21/2022 APPLICANT
CofO in Progress 7/31/2024 ALFREDO LOPEZ
CofO Issued 8/5/2024 ERNESTO CORRAL
Permit Finaled 8/5/2024 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/26/2022 JEANIE LAM
Sewer availability Cleared 9/26/2022 JEANIE LAM
ZI Cleared 9/28/2022 YINGSHI HUANG
Address approval Cleared 9/29/2022 JEANIE LAM
Green Code Cleared 10/4/2022 MICHAEL AYERS
Specific Plan Cleared 10/27/2022 MOHAMMAD HASAN
Specific Plan Cleared 11/10/2022 DANIEL MATA
ZI Cleared 11/10/2022 DANIEL MATA
Low Impact Development Cleared 11/14/2022 ANTHONY VARGAS
Tenant Habitability Plan Cleared 11/16/2022 MICHAEL SOTO
Roof/Waste drainage to street Cleared 11/18/2022 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Yiu,, Siu Fung; Lic. No.: S5801 PO BOX 5143      EL MONTE, CA 91734

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2023 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Barrier 2/7/2023 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Subgrade 2/7/2023 Not Ready for Inspection MARTIN TAVITIAN
Footing/Foundation/Slab 2/23/2023 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Barrier 2/23/2023 Not Ready for Inspection MARTIN TAVITIAN
METHANE-Subgrade 2/23/2023 Approved MARTIN TAVITIAN
METHANE-Rough 3/21/2023 Conditional Approval DARRYL ARNOLD
METHANE-Rough 3/23/2023 Not Ready for Inspection MARTIN TAVITIAN
Deputy Drilled-In Anchors 4/10/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 5/1/2023 Approved ALAN MORELOS
METHANE-Barrier 5/1/2023 Approved ALAN MORELOS
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Partial Approval MARTIN TAVITIAN
Green Building Rough 7/5/2023 Approved MARTIN TAVITIAN
METHANE-Rough 7/5/2023 Approved MARTIN TAVITIAN
Wood Frame 7/5/2023 Not Ready for Inspection MARTIN TAVITIAN
Wood Frame 7/14/2023 Not Ready for Inspection ALAN MORELOS
Insulation 7/18/2023 Not Ready for Inspection MARTIN TAVITIAN
Insulation 7/21/2023 Approved MARTIN TAVITIAN
Drywall Nailing 7/24/2023 Not Ready for Inspection MARTIN TAVITIAN
Insulation 7/24/2023 Approved MARTIN TAVITIAN
Drywall Nailing 7/25/2023 Not Ready for Inspection MARTIN TAVITIAN
Drywall Nailing 7/26/2023 Not Ready for Inspection ALAN MORELOS
Drywall Nailing 7/26/2023 Not Ready for Inspection MARTIN TAVITIAN
Drywall Nailing 7/27/2023 Approved MARTIN TAVITIAN
Drywall Nailing 7/31/2023 Approved MARTIN TAVITIAN
Pre-Inspection 8/11/2023 Partial Approval MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 8/14/2023 SGSOV Not Ready MARTIN TAVITIAN
Pre-Inspection 8/17/2023 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 8/24/2023 SGSOV Not Ready MARTIN TAVITIAN
Pre-Inspection 8/25/2023 Approved MARTIN TAVITIAN
Pre-Inspection 8/31/2023 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Not Ready MARTIN TAVITIAN
Pre-Inspection 9/5/2023 Not Ready for Inspection MARTIN TAVITIAN
Pre-Inspection 9/6/2023 Partial Approval MARTIN TAVITIAN
Final 5/30/2024 Not Ready for Inspection ALFREDO LOPEZ
Green Building Final 5/30/2024 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 5/30/2024 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 5/30/2024 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 5/30/2024 Approved ALFREDO LOPEZ
Final 6/13/2024 Partial Approval ALFREDO LOPEZ
Green Building Final 6/13/2024 Approved ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 6/13/2024 SGSOV Approved ALFREDO LOPEZ
Smoke Detectors 6/13/2024 Approved ALFREDO LOPEZ
Final 6/21/2024 Partial Approval ALFREDO LOPEZ
Final 7/2/2024 Not Ready for Inspection ALFREDO LOPEZ
Final 7/31/2024 OK to Issue CofO ALFREDO LOPEZ