1185-1189 1/2 W 28TH ST 90007
Certificate Information: 1185-1189 1/2 W 28TH ST 90007
- Application / Permit
- 22016-20000-27759
- Plan Check / Job No.
- B22VN13909
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN: PROPOSED REMODEL AND ADDITION OF ACCESSORY DWELLING UNIT TO APARTMENT BUILDING PER LAMC 12.22 A.33(c) and (e); NFPA-13 FIRE SPRINKLER IS REQUIRED
- Permit Issued
- Issued on 12/21/2022
- Issuing Office
- Current Status
- CofO Issued on 8/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/15/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 9/15/2022 | SINA KHOSRAVI |
| Corrections Issued | 9/19/2022 | SINA KHOSRAVI |
| Quality Review Completed | 9/21/2022 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 10/7/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 10/25/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 11/29/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 12/6/2022 | SINA KHOSRAVI |
| Plan Check Approved | 12/21/2022 | SINA KHOSRAVI |
| Issued | 12/21/2022 | APPLICANT |
| CofO in Progress | 7/31/2024 | ALFREDO LOPEZ |
| CofO Issued | 8/5/2024 | ERNESTO CORRAL |
| Permit Finaled | 8/5/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/26/2022 | JEANIE LAM |
| Sewer availability | Cleared | 9/26/2022 | JEANIE LAM |
| ZI | Cleared | 9/28/2022 | YINGSHI HUANG |
| Address approval | Cleared | 9/29/2022 | JEANIE LAM |
| Green Code | Cleared | 10/4/2022 | MICHAEL AYERS |
| Specific Plan | Cleared | 10/27/2022 | MOHAMMAD HASAN |
| Specific Plan | Cleared | 11/10/2022 | DANIEL MATA |
| ZI | Cleared | 11/10/2022 | DANIEL MATA |
| Low Impact Development | Cleared | 11/14/2022 | ANTHONY VARGAS |
| Tenant Habitability Plan | Cleared | 11/16/2022 | MICHAEL SOTO |
| Roof/Waste drainage to street | Cleared | 11/18/2022 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yiu,, Siu Fung; Lic. No.: S5801 | PO BOX 5143 EL MONTE, CA 91734 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/7/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Barrier | 2/7/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Subgrade | 2/7/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 2/23/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Barrier | 2/23/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Subgrade | 2/23/2023 | Approved | MARTIN TAVITIAN |
| METHANE-Rough | 3/21/2023 | Conditional Approval | DARRYL ARNOLD |
| METHANE-Rough | 3/23/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Deputy Drilled-In Anchors | 4/10/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 5/1/2023 | Approved | ALAN MORELOS |
| METHANE-Barrier | 5/1/2023 | Approved | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Partial Approval | MARTIN TAVITIAN |
| Green Building Rough | 7/5/2023 | Approved | MARTIN TAVITIAN |
| METHANE-Rough | 7/5/2023 | Approved | MARTIN TAVITIAN |
| Wood Frame | 7/5/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 7/14/2023 | Not Ready for Inspection | ALAN MORELOS |
| Insulation | 7/18/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Insulation | 7/21/2023 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 7/24/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Insulation | 7/24/2023 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 7/25/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Drywall Nailing | 7/26/2023 | Not Ready for Inspection | ALAN MORELOS |
| Drywall Nailing | 7/26/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Drywall Nailing | 7/27/2023 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 7/31/2023 | Approved | MARTIN TAVITIAN |
| Pre-Inspection | 8/11/2023 | Partial Approval | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 8/14/2023 | SGSOV Not Ready | MARTIN TAVITIAN |
| Pre-Inspection | 8/17/2023 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 8/24/2023 | SGSOV Not Ready | MARTIN TAVITIAN |
| Pre-Inspection | 8/25/2023 | Approved | MARTIN TAVITIAN |
| Pre-Inspection | 8/31/2023 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2023 | SGSOV Not Ready | MARTIN TAVITIAN |
| Pre-Inspection | 9/5/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Pre-Inspection | 9/6/2023 | Partial Approval | MARTIN TAVITIAN |
| Final | 5/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 5/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/30/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 5/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 5/30/2024 | Approved | ALFREDO LOPEZ |
| Final | 6/13/2024 | Partial Approval | ALFREDO LOPEZ |
| Green Building Final | 6/13/2024 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 6/13/2024 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 6/13/2024 | Approved | ALFREDO LOPEZ |
| Final | 6/21/2024 | Partial Approval | ALFREDO LOPEZ |
| Final | 7/2/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 7/31/2024 | OK to Issue CofO | ALFREDO LOPEZ |