7510 W 91ST ST 90045

Certificate Information: 7510 W 91ST ST 90045

Application / Permit
22016-20000-27734
Plan Check / Job No.
B22VN13896
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EX. 22' x 20'1" GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP
Permit Issued
Issued on 2/21/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/14/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 JEFFREY TANGONAN
Corrections Issued 9/16/2022 JEFFREY TANGONAN
Building Plans Picked Up 9/20/2022 APPLICANT
Plan Check Approved 11/30/2022 OMAR GARNICA
Issued 2/21/2023 APPLICANT
CofO in Progress 9/15/2023 BOBBY KEY
Permit Finaled 9/21/2023 DANIEL ORRANTE
CofO Issued 9/21/2023 DANIEL ORRANTE
Permit Finaled 9/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/11/2022 DENNIS BRAGIN
Sewer availability Cleared 10/11/2022 DENNIS BRAGIN
Construction near power lines Cleared 11/17/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 11/22/2022 DENNIS BRAGIN
Specific Plan Cleared 11/23/2022 PEDRO AYALA

Contact Information

Architect Saivar,, Timothy Martin; Lic. No.: C13727 15594 MALLORY CT      MOORPARK, CA 93021
Contractor H P T N Construction; Lic. No.: 1058516-B 115 ACACIA LN      NEWBURY PARK, CA 91320

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/9/2023 Not Ready for Inspection BOBBY KEY
PLUMBING-Rough 3/9/2023 Partial Approval BOBBY KEY
Footing/Foundation/Slab 3/14/2023 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 3/14/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 3/20/2023 Conditional Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Approved BOBBY KEY
Footing/Foundation/Slab 4/10/2023 Approved BOBBY KEY
Underground Mechanical 4/10/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 4/24/2023 Approved BOBBY KEY
BUILDING-Rough-Frame 4/27/2023 Conditional Approval BOBBY KEY
Green Building Rough 4/27/2023 Corrections Issued BOBBY KEY
HVAC-Rough 4/27/2023 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 4/27/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 4/27/2023 Corrections Issued BOBBY KEY
BUILDING-Rough-Frame 5/4/2023 Approved BOBBY KEY
Green Building Rough 5/4/2023 Approved BOBBY KEY
HVAC-Rough 5/4/2023 Approved BOBBY KEY
Insulation 5/4/2023 Approved BOBBY KEY
PLUMBING-Rough 5/4/2023 Approved BOBBY KEY
Drywall Nailing 5/12/2023 Approved BOBBY KEY
ELECTRICAL-Rough 5/26/2023 Partial Inspection KENNETH NAGLE
ELECTRICAL-Final 9/5/2023 Corrections Issued HERBERT GIRON
Final 9/5/2023 Corrections Issued HERBERT GIRON
HVAC-Final 9/5/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 9/5/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 9/5/2023 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 9/5/2023 Approved HERBERT GIRON
ELECTRICAL-Final 9/12/2023 Not Ready for Inspection BOBBY KEY
Final 9/12/2023 No Access for Inspection BOBBY KEY
HVAC-Final 9/12/2023 No Access for Inspection BOBBY KEY
PLUMBING-Final 9/12/2023 Not Ready for Inspection BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/12/2023 SGSOV Not Ready BOBBY KEY
ELECTRICAL-Final 9/15/2023 Approved BOBBY KEY
Final 9/15/2023 OK to Issue CofO BOBBY KEY
HVAC-Final 9/15/2023 Approved BOBBY KEY
PLUMBING-Final 9/15/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 9/15/2023 SGSOV Approved BOBBY KEY