18051 W SHERMAN WAY 91335

Certificate Information: 18051 W SHERMAN WAY 91335

Application / Permit
22016-20000-27691
Plan Check / Job No.
B22VN13873
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(8) Auto Repair Garage
Work Description
TENANT IMPROVEMENT TO (E) AUTOMOTIVE REPAIR TO INCLUDE NEW BATHROOMS/INTERIOR LAYOUT AND DOORS, REMOVE (E) MEZZANINE AND EXTERIOR WORK TO INCLUDE NEW WINDOWS AND REMOVING (E) SIGNAGE.
Permit Issued
Issued on 4/3/2023
Issuing Office
Valley
Current Status
Permit Finaled on 1/9/2024

Permit Application Status History

Submitted 9/14/2022 APPLICANT
Assigned to Plan Check Engineer 9/15/2022 PETER MOSESIAN
Corrections Issued 9/17/2022 PETER MOSESIAN
Quality Review Completed 9/20/2022 OMID HEDAYAT
Building Plans Picked Up 9/22/2022 APPLICANT
Disabled Access Plans Picked Up 9/22/2022 APPLICANT
Green Plans Picked Up 9/22/2022 APPLICANT
Plan Check Approved 12/8/2022 PETER MOSESIAN
Issued 4/3/2023 APPLICANT
Permit Finaled 1/8/2024 BRIAN KELLY

Permit Application Clearance Information

CPC Cleared 9/22/2022 NATHAN ROMINE
"Q" conditions Cleared 9/26/2022 NATHAN ROMINE
ZI Cleared 11/30/2022 COURTNEY YELLEN
Green Code Cleared 12/1/2022 MICHAEL AYERS
DAS Clearance Cleared 12/5/2022 NORLITO MEDRANO

Contact Information

Architect Shremshock,, Gerald S; Lic. No.: C27005 SHREMSHOCK ARCHITECTS INC.   7400 W. CAMPUS RD. STE. 150    NEW ALBANY, OH 43054
Contractor Daniar Construction Group Inc; Lic. No.: 1054728-B 25852 MCBEAN PARKWAY #204      VALENCIA, CA 91355

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/8/2023 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 5/16/2023 Not Ready for Inspection BRIAN KELLY
Wood Frame 5/16/2023 Not Ready for Inspection BRIAN KELLY
Light Gage Steel Frame 5/22/2023 Partial Approval BRIAN KELLY
Wood Frame 5/22/2023 Partial Approval BRIAN KELLY
Light Gage Steel Frame 6/2/2023 Partial Approval BRIAN KELLY
Drywall Nailing 6/7/2023 Partial Approval BRIAN KELLY
Light Gage Steel Frame 6/21/2023 Partial Approval BRIAN KELLY
Drywall Nailing 6/23/2023 Partial Approval BRIAN KELLY
Light Gage Steel Frame 6/30/2023 Partial Approval BRIAN KELLY
Drywall Nailing 7/13/2023 Partial Approval BRIAN KELLY
Light Gage Steel Frame 7/21/2023 Approved BRIAN KELLY
T-Bar Ceiling 9/6/2023 Approved STEVEN LEVITT
T-Bar Ceiling 9/29/2023 Approved ANDREW DORSO
Final 12/28/2023 Not Ready for Inspection BRIAN KELLY
Green Building Final 12/28/2023 Not Ready for Inspection BRIAN KELLY
Green Building Rough 12/28/2023 Approved BRIAN KELLY
Reinforced Masonry Frame 12/28/2023 Approved BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 12/28/2023 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 12/28/2023 Not Ready for Inspection BRIAN KELLY
Final 1/8/2024 Permit Finaled BRIAN KELLY
Green Building Final 1/8/2024 Approved BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 1/8/2024 SGSOV Approved BRIAN KELLY
Smoke Detectors 1/8/2024 Approved BRIAN KELLY